Mount Lebanon Township, Pennsylvania Building Permit Guide

To get a building permit in Mount Lebanon Township, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Mt. Lebanon’s Inspection Office, on the second floor of the Municipal Building at 710 Washington Road, reviews plans and issues building and zoning permits, with online applications through Municity Connect.

Authority: Mt. Lebanon Inspection OfficeCode: Pennsylvania UCC, opted in 2004Phone: 412-343-3408
Authority
Inspection Office710 Washington Road, 2nd floor
Apply Online
Municity ConnectThrough MyLebo
Typical timing
15 business daysResidential; commercial 30 days
New house fee
$0.94 per sq ft2026 fee schedule R-16-25

In Mt. Lebanon the municipality’s own Inspection Office, 710 Washington Road, second floor (412-343-3408, weekdays 8:30 a.m. to 5 p.m.), reviews plans, issues building and zoning permits and inspects the work; applications can be filed online through Municity Connect from the MyLebo portal or on paper. Residential permits are generally issued within 15 business days, and under the 2026 fee schedule (R-16-25) an addition costs $60 for the first $1,000 plus $7.50 per $1,000 after that, or $0.70 a square foot if that is more.

What requires a building permit in Mt. Lebanon?

Mt. Lebanon’s rule is to get a permit before constructing, altering, replacing or repairing an existing structure, and every commercial project needs one. Owners who start without a permit face fines set by the magisterial district judge and, under the fee schedule, a doubled permit fee of up to $1,000 per permit. The Inspection Office publishes project-by-project guidance for the most common jobs, summarized below.

Building permit

  • Additions, decks and hot tubs
  • Structural roof repairs and window replacements
  • Front porches and stairs on the path from the front door to the street
  • Porch enclosures, three-season or full rooms
  • Kitchen and bath remodels
  • Storage sheds of any size
  • Retaining walls over 2 feet (engineering drawings over 4 feet)
  • Sump pumps and interior drain systems
  • Solar panels, wall anchors and push piers
  • Pools, above-ground and in-ground

Zoning permit or no permit

  • Fences, driveways and parking pads, air conditioners: zoning permit
  • Patios at grade, bees, chickens and tree houses: zoning permit
  • A dumpster on your own property: no permit
  • Portable storage pods for 10 days while moving: no permit
  • Temporary window signs covering no more than 25% of a window: no permit

Zoning limits ride along with these permits. In single-family districts fences up to 6 feet are allowed in side and rear yards and none in front yards, solid fences are not allowed, shadowbox fences may be 4 feet, and a fence may sit on the property line. Sheds must be 5 feet from property lines and out of the front setback, patios 5 feet from property lines, and a front porch may project no more than 10 feet into the front yard. Patios adding more than 500 square feet of impervious area must also meet the stormwater ordinance. One inconsistency: the shed guidance calls for a building permit for any storage shed, while the fee schedule and the permit-timing note list sheds among the $90 zoning permits, so the Inspection Office decides which applies.

What Mt. Lebanon decides and what the state holds

Mt. Lebanon, a home rule municipality, opted in to the Uniform Construction Code on June 28, 2004 and is listed by the Department of Labor and Industry with local amendments. The state code sets the construction standards; the municipality sets its zoning (fence rules sit in Chapter 20, section 808), grading, health and safety, minimum property standards and stormwater rules, the stormwater fee ordinance first approved in 2011 and last amended on December 12, 2023, and the comprehensive fee schedule adopted each year.

Short on time to read all of this?

Get a free quote →

Mt. Lebanon building department: who handles permitting

The Inspection Office oversees all residential and commercial construction, new and remodeling, and also enforces the grading, health and safety, minimum property standards, solid waste and zoning chapters of the Mt. Lebanon Code. Its building and zoning inspectors review applications; electrical permits and inspections are handled by Middle Department Inspection Agency (MDIA), and plumbing by the Allegheny County Health Department, with each sending proof of approval to the Inspection Office.

Mt. Lebanon Inspection Office contacts
DetailInformation
OfficeInspection Office, Municipal Building, 710 Washington Road, second floor, Pittsburgh, PA 15228
Phone412-343-3408 (permits and inspection requests); building inspector 412-343-3468
HoursMonday to Friday, 8:30 a.m. to 5 p.m.
Online applicationsMunicity Connect, reached through MyLebo (“Inspections Department Permits”)
ElectricalMiddle Department Inspection Agency, 1-800-362-6342
PlumbingAllegheny County Health Department Plumbing Program, 412-578-8123 (in-person permit office, 412-578-8036)
Code enforcement412-343-4584

Mt. Lebanon permit types

Each application on the municipality’s permits page carries a checklist. Besides the residential and commercial building permit applications there are forms for a certificate of occupancy and use, demolition, driveways and parking pads, fences, front porches and stairs, grading, home occupations, bees and chickens, mechanical work (air conditioning, furnaces, generators), patios, portable storage pods, pools, porch enclosures, kitchen and bath remodels, new houses, retaining walls, sheds, signs, sump pumps and interior drains, solar panels, wall anchors and push piers, and zoning variances. Municity Connect lets users apply, upload drawings, request inspections, submit complaints and track items online; both a MyLebo and a Municity Connect account are needed, and online payment had not yet launched.

Residential permits

Zoning permits and many building permits need a property survey, a certified, dimensioned drawing of the lot; the Inspection Office holds surveys only for properties where an earlier permit required one, so the owner provides it, and most forms ask for two copies. New houses start with zoning compliance before the building application, are reviewed against the stormwater and grading ordinances, and most need a developer’s agreement with securities posted. Solar arrays need a stamped design from a Pennsylvania design professional, as do most wall anchor and push pier jobs, and replacement basement floors over interior drains are inspected for a minimum 3½-inch thickness.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

All commercial projects require permits. Fees run $110 for the first $1,000 of estimated cost plus $7.50 per $1,000, and new commercial buildings pay that or $0.99 a square foot, whichever is greater; commercial plan review is $110 for the first 10 sheets plus $5.25 a sheet. Signage regulated by the state building code uses the commercial building permit application, and commercial demolition needs utility releases and an asbestos exemption or abatement certificate. A certificate of occupancy is required for a change of use in an existing building or of a nonconforming use.

What comes before the building permit

  • Zoning. Zoning permits for air conditioners, driveways, fences and sheds are issued within 30 days; variances go to the Zoning Hearing Board ($500 for 1–4 dwelling units, $1,000 for other uses).
  • Stormwater. Projects adding 500 to 1,500 square feet of impervious surface pay a $250 stormwater review; larger ones pay $100 plus an escrow for the third-party engineer.
  • Grading. One-family sites pay $260 for a grading permit; other sites $465 up to 1,000 cubic yards plus $47 per additional 1,000.
  • Historic review. Federally funded or permitted projects affecting historic properties go through Section 106 review; requests go to the staff liaison to the Resiliency Advisory Board, and the municipality’s Design Guide covers older homes.
  • Streets and dumpsters. A dumpster in the street needs a permit from the Police Traffic Division (412-343-4086); street openings are $90 plus $1.50 per additional foot.

Mt. Lebanon permit costs and fees

Mt. Lebanon adopts a comprehensive fee schedule every year. The 2026 schedule, R-16-25, is the one in force; a 2027 schedule posted in October 2026 is still labeled proposed, so 2026 rates apply until the Commission adopts it.

Rather talk it over?

Call 1-855-478-4290 →
Mt. Lebanon inspection fees (2026 Comprehensive Fee Schedule, R-16-25)
ItemFee
New single-family house$0.94 per sq ft
Additions and renovations (incl. pools)$60 for the first $1,000 + $7.50 per $1,000, or $0.70 per sq ft if greater
Commercial and multi-family$110 for the first $1,000 + $7.50 per $1,000; new buildings or $0.99 per sq ft if greater
State UCC fee$4.50 per building permit
Mechanical, residential$40 for the first $1,000 + $6.20 per $1,000; generator $90
Mechanical, commercial$50 for the first $1,000 + $5 per $1,000
Residential zoning permit (fence, driveway, A/C, shed, tree house, apiary)$90
Demolition$260 house under 1,000 sq ft; $310 over; commercial $620 + $0.77 per sq ft
Occupancy permit$80 residential + $40 per reinspection; $155 commercial + $105
Failed inspection$50 residential; $110 commercial
Permit extension$100 residential; $500 commercial
Stormwater review$250 (500–1,500 sq ft); $100 + engineer escrow above
Work started without a permitDouble the permit fee, up to $1,000 per permit
Sanitary sewer tap-in$100 per EDU
Commercial plan review$110 for the first 10 sheets + $5.25 per additional sheet
Grading$260 one-family site; $465 other sites up to 1,000 cu yd, + $47 per extra 1,000
Annual swimming pool operation permit$42

Worked example: a 300-square-foot addition costing $30,000 is charged $60 for the first $1,000 plus 29 × $7.50, or $277.50; the area test gives 300 × $0.70, or $210, so the higher $277.50 applies, plus the $4.50 state fee for $282. A new 2,000-square-foot house is 2,000 × $0.94, or $1,880, before the state fee, zoning, stormwater, grading and occupancy charges.

Trade permits and who may pull them

  • Electrical: permits and inspections are obtained from and performed by Middle Department Inspection Agency (1-800-362-6342) under the National Electrical Code; MDIA sends proof of approval to the Inspection Office. Pools, illuminated signs and service changes all need the electrical permit.
  • Plumbing: the Allegheny County Health Department’s plumbing program issues a separate permit, approves the plumbing plan and inspects under the county plumbing code; kitchen and bath remodels need both its permit and the municipal building permit.
  • Mechanical: air conditioners, furnaces and generators take the municipal mechanical permit, priced on installation cost.
  • Rough-ins: electrical, plumbing and mechanical inspections each consist of a rough-in and a final.

Mt. Lebanon’s pages show no municipal trade license; its Historic Home page offers advice on choosing a contractor, and home improvement contractors register with the Attorney General under state law.

Rather not deal with the building department?

Get a free quote →

How to apply for a Mt. Lebanon building permit

1. Book a consultation if needed

30-minute Inspections Consultations run on the first Wednesday of each month, 2 to 5 p.m.; register at 412-343-3408 by 4 p.m. the Friday before.

2. Get a survey

Most zoning and building permits need a property survey marked with the work.

3. Pick the project form

Use the checklist on the matching application (deck, shed, porch, remodel, new house).

4. Apply

File online in Municity Connect through MyLebo, or drop the paper application at 710 Washington Road.

5. Review and notice

The office emails or calls when the permit is ready and tells you the amount due.

6. Pay and post

Pay by Visa, MasterCard, exact cash or check, display the permit card in a front window and keep the approved plans on site.

Review, corrections and what causes delay

The municipality aims to issue residential building permits within 15 business days, commercial permits within 30 days and zoning permits within 30 days. Incomplete applications are the delay the consultations are meant to prevent, and new houses wait on zoning compliance, stormwater and grading review and the developer’s agreement. Applications are processed in the order they are received.

Inspections in Mt. Lebanon

Request inspections by calling 412-343-3408; requests cannot be left on voicemail. Inspectors go out twice a day, Monday to Friday, from 10 a.m. to noon and from 2 to 4 p.m., so call before those windows with the address and inspection type. The stages for new work are the footer inspection before concrete, with rebar in place and footings on undisturbed ground at least 3 feet below finished grade (plus a foundation survey for new buildings); rough framing after the electrical and plumbing rough-ins but before insulation; storm drainage before it is covered; insulation; drywall before finishing; and the final. A certificate of occupancy, applied for with the building permit when needed, is released by the building inspector before a new building or addition is occupied.

Before selling a home

Close out every permit before a sale: Mt. Lebanon will not issue a lien letter while permits are open. Point-of-sale dye testing is run by Public Works (412-343-3403); the evidence of compliance must be submitted at least 10 business days before closing with a $50 fee.

Pennsylvania building code

Mt. Lebanon chose to enforce the Uniform Construction Code locally on June 28, 2004, with amendments. FEMA’s Community Status Book lists the Municipality of Mt. Lebanon (community 421272) as participating in the National Flood Insurance Program, with a current map dated September 26, 2014 that FEMA marks as having no elevations.

Want this handled start to finish?

Get a free quote →

Pennsylvania has one Uniform Construction Code for the whole state, based on the 2021 International Codes since January 1, 2026. Most municipalities enforce it themselves or through a certified third-party agency; where a municipality has opted out, the Department of Labor and Industry handles commercial work and home owners hire a certified agency. Counties do not issue building permits. Pennsylvania rules

Mt. Lebanon permit search and official resources

Permit applications filed through Municity Connect can be tracked online by the applicant. Other records, including older permit files and surveys the Inspection Office holds ($5 a copy on site), can be requested on the standard state right-to-know form or on Mt. Lebanon’s own public records request form, under the municipality’s resolution on requests.

Inspections are where schedules slip.

Get a free quote →

Mt. Lebanon building permit FAQs

Can I apply for a Mt. Lebanon permit online?

Yes, through Municity Connect from the MyLebo portal; you need accounts on both. Paper applications are also accepted at 710 Washington Road.

How long does a permit take?

Residential building permits are generally issued within 15 business days, commercial permits within 30 days and zoning permits within 30 days.

Do I need a permit to replace windows?

Yes. Mt. Lebanon lists window replacements, structural roof repairs, decks, hot tubs and additions among the work needing a building permit.

Do I need a permit for a shed?

Yes, but the municipality’s papers differ on which one: the shed handout calls for a building permit for any storage shed, while the 2026 fee schedule lists sheds among the $90 zoning permits. Ask the Inspection Office which applies. Sheds must be 5 feet from the property lines and out of the front setback.

How tall can my fence be?

Up to 6 feet in side and rear yards in single-family districts; no fences in front yards and no solid fences. A $90 zoning permit is needed.

How do I schedule an inspection?

Call 412-343-3408 (no voicemail); inspections run weekdays 10 a.m. to noon and 2 to 4 p.m.

Who handles electrical permits?

Middle Department Inspection Agency, at 1-800-362-6342.

Simplify Mount Lebanon Township permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Pennsylvania. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Mount Lebanon Township sooner?

Let Alliance prepare, file, and track your Mount Lebanon Township permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Mount Lebanon Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.