Bethlehem Township, a separate municipality from the City of Bethlehem, handles building, zoning and fire permits through its Community Development Department at the Municipal Building, 4225 Easton Avenue (610-814-6435), led by Director Samantha Smith. Township residential and commercial construction officials do the plan review and inspections; only electrical work goes to a third-party agency, Keycodes. Fees come from the schedule effective June 1, 2025: new houses pay $0.70 a square foot with a $1,000 minimum, and every application starts with a $100 submittal fee that is credited if the permit is approved.
What requires a building permit in Bethlehem Township?
The township sorts work into two groups on its permits page: projects that need only a zoning permit, and projects that need a construction permit under the UCC and township ordinances. It notes the list is not complete and that work excluded from the UCC may still need zoning approval.
Construction permit
- Structural changes and alterations, finished basements and living-space conversions
- Plumbing, electrical and mechanical work, including replacement HVAC equipment and water heaters
- Replacement windows, and reroofing on commercial buildings
- Decks 30 inches or more above grade, and patio roofs
- Pools (permanent and temporary), hot tubs and spas
- Retaining walls over 48 inches
Zoning permit only
- Detached garages, sheds and other accessory structures under 1,000 square feet
- Decks under 30 inches above grade, and patios
- Driveway expansions or additions
- Fences, temporary or permanent
- Retaining walls of 48 inches or less
Residential reroofing is not on the construction permit list, which names reroofing for commercial buildings only. A basement finish needs a permit for each trade being installed or extended, and a building permit as well if it includes structural changes or a new egress window. The application asks whether the property is in a FEMA floodplain; flood permits, where required, are priced under HRG’s fee schedule.
What Bethlehem Township decides and what the state holds
The township opted in to UCC enforcement on June 21, 2004, with no local amendments on L&I’s list. Its Board of Commissioners adopted Ordinance 03-26 on February 16, 2026, updating Chapter 110 of the township code to the UCC’s new edition of the International Codes, and Ordinance 02-26 the same night, adopting the 2021 International Property Maintenance Code; the permits page still cites the 2018 codes. The Board sets fees by resolution, and on June 1, 2026 it adopted Ordinance 06-26, a zoning amendment adding new uses, which the director later described as setting standards for data centers.
Bethlehem Township building department: who handles permitting
The township does, with its own staff. The Community Development Department combines planning, zoning and the construction officials: a Residential Construction Official reviews and inspects house projects, and a Commercial Construction Official handles commercial, industrial and institutional work and acts as the fire code official. Electrical work is the one trade overseen by a third party, Keycodes Inspection Agency, and flood permits are reviewed under HRG’s fee schedule.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Community Development Department, Municipal Building, 4225 Easton Avenue, Bethlehem, PA 18020 |
| Phone | Community Development 610-814-6435; township main line 610-814-6400 |
| Permit counter | Monday to Friday, 8 a.m. to 4 p.m.; cash or check for resale certificates |
| Director | Samantha Smith, Community Development Director |
| Resale and rental inspections | Code Enforcement Officer, 610-814-6467 |
| Electrical agency | Keycodes Inspection Agency, Bethlehem; 610-866-9663 |
| Public sewer | Bethlehem Township Municipal Authority (BTMA) |
The township’s interactive mapping system shows a parcel’s number, dimensions and zoning; ownership and sales records come from Northampton County, whose land use codes are for tax purposes and are not the township’s zoning.
Bethlehem Township permit types
One building permit application covers building, mechanical, plumbing, electrical and fire protection work, with addenda for pools, decks and basements. Applications missing required information are treated as incomplete and are not reviewed. Separate forms cover sewer connections, street openings, Board of Appeals hearings, temporary certificates of occupancy, home occupations and the resale and lease inspection program.
Residential permits
The residential process runs in seven steps: submit the complete application, township code review, requests for more information if needed, notice of the fee once approved, payment and permit pick-up, inspections booked with the township, and a certificate of occupancy or certificate of compliance after the last inspection. Fees for houses are based on gross floor area, which counts the basement, garage, each floor, porches, patios and attached decks.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial packages go in person or by first-class mail: the signed building permit application and a separate electrical permit application for Keycodes, two sets of plans (most sealed by a Pennsylvania architect or engineer, with electrical drawings kept separate), two copies of COMcheck energy documents, sprinkler and standpipe drawings sealed by a NICET Level III or IV technician or registered design professional, fire alarm certification from a recognized testing laboratory, and geotechnical reports where needed. Elevators and boilers over 199,000 BTU need L&I approval, new buildings a BTMA sewer connection application and water approvals, and blasting a township permit with DEP approval. The code official may require a Knox box.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. Uses permitted by right are approved by the Zoning Officer; special exceptions and variances go to the Zoning Hearing Board ($750 for a single-family home, $1,000 otherwise), and conditional uses to a public hearing before the governing body ($1,000).
- Grading. A new single-family house needs a grading permit for its individual lot grading plan ($800, or $1,200 with an NPDES permit); other earth disturbance is $450, and adding impervious surface after occupancy $250 or $400.
- Sewer and septic. Public sewer connections go through BTMA, which also posts a septic certification form and hauler list for properties on septic.
- Streets and driveways. A driveway zoning permit ($100) needs a separate street opening permit from Public Works.
- Subdivision and land development. Sketch plans $240, minor subdivisions $500 and preliminary or final plans $1,200, plus escrows starting at $5,000.
Bethlehem Township permit costs and fees
The fee schedule in force took effect on June 1, 2025; the only 2026 amendment, Resolution R039-26 of April 20, 2026, changed police fees. Work begun without a permit pays double. Standard permit fees include the required inspections and one re-inspection; further re-inspections cost $50 per trade.
| Item | Fee |
|---|---|
| Permit application submittal (credited toward the permit if approved) | $100, nonrefundable |
| New single-family, twin or townhome | $0.70 per sq ft, $1,000 minimum |
| Structural alterations, additions, covered decks, decks over 30 inches | $0.50 per sq ft, $250 minimum |
| Accessory structure (construction permit) | $0.60 per sq ft |
| Mechanical permit / fuel-fired water heater | $175 / $75 |
| Plumbing | $150 minimum; new fixtures $30 each, replaced $20 each |
| Pool: above-ground 24 in. and over / in-ground / hot tub | $200 / $500 / $200 |
| Solar: roof-mounted / ground-mounted, up to 5 kW | $300 / $400 |
| Minimum job fee / plan review | $125 / $75 per hour minimum |
| Demolition | $220 |
| Certificate of occupancy: residential / non-residential up to 2,000 sq ft | $100 / $130 plus $30 per extra 1,000 sq ft |
| Zoning permits: accessory structure / deck or patio / fence / driveway | $150 / $100 / $100 / $100 |
| Third-party administration fee: commercial / residential electrical | 25% of total permit cost / $50 |
| Commercial building, fire and electrical permits | Keycodes Inspection Agency fee schedule |
| PA UCC fee | $4.50 |
Rather talk it over?
Call 1-855-478-4290 →Worked examples: a new 2,400-square-foot house (counting basement, garage and porches) costs 2,400 × $0.70 = $1,680, above the $1,000 minimum, plus the $4.50 UCC fee, with the $100 submittal fee credited toward it; electrical inspection is billed under Keycodes’ schedule plus the township’s $50 administration fee. A 300-square-foot addition works out to $150 at $0.50 a square foot, so the $250 minimum applies. A winter escrow of $1,000 applies when final grading, seeding and the driveway must wait for warmer weather.
Other house items on the schedule: an industrialized (modular) home is $0.40 a square foot with a $400 minimum, a seasonal or storable pool $200 for the first set-up and $50 each later season, a pool deck $150, a replacement pool barrier $100 and a wind turbine $250 with a design professional’s seal. New homes in a subdivision also carry a recreation fee of $1,500 per unit ($3,500 per acre for non-residential land). A Zoning Hearing Board fee is refunded in full if the application is withdrawn before the hearing is advertised, and 25% is returned after that; a continuance not caused by the township costs $250 for a single-family home and $500 otherwise.
Trade permits and who may pull them
Plumbing and mechanical permits are reviewed and inspected by township officials; electrical permits are handled by Keycodes, under its fee schedule plus the township’s administration fee. The application lists general, electrical, fire protection, mechanical and plumbing contractors separately. The township’s pages show no local trade license; home improvement contractors carry their own HICPA registration.
- Electrical: commercial work needs a separate signed electrical application; for houses the township adds a $50 administration fee to the agency’s charge.
- Plumbing: $150 minimum, new sanitary connections and sewer or water service repairs $150 each.
- Mechanical: $175 covers plan review and inspection of fuel-fired appliances, gas generators, pool heaters, oil tanks, HVAC, geothermal, solar hot water, fireplaces and stoves.
- Fire protection: residential sprinklers $20 a head ($100 minimum) and sealed by a registered design professional; commercial fire permits follow the Keycodes schedule.
Rather not deal with the building department?
Get a free quote →How to apply for a Bethlehem Township building permit
Confirm district, setbacks and any floodplain on the township’s mapping system.
Use the building permit application and any pool, deck or basement addendum.
File with the $100 nonrefundable submittal fee at the Municipal Building permit counter.
The township contacts the applicant if more information is needed.
Once approved, pay the balance of the fee and pick up the permit.
Contact the township for each required inspection, then receive the certificate.
Review, corrections and what causes delay
The township commits to a response within 15 business days once a residential application is complete; commercial applications have 30 working days. Incomplete applications are not reviewed at all, and the township says it is not responsible for keeping them. Grading plans include two pre-construction reviews; each further review costs $200, and a final as-built plan changed without approval costs $450 to re-review.
Inspections in Bethlehem Township
After the permit is issued, the applicant contacts the township for each required inspection, and a certificate of occupancy or compliance follows the final one. The fee includes one failed-inspection re-check; any further re-inspection, including for work not ready, costs $50 per trade and must be paid before the visit.
Bethlehem Township requires an inspection and certificate of occupancy when a property is sold, rented or leased. For homes, the owner or agent files the Property Resale/Lease Inspection application with the $100 fee (cash or check) at the permit counter; the Code Enforcement Officer then schedules the visit between 9 a.m. and 3 p.m. on a weekday, and someone must meet the officer on site. The seller passes the results to the buyer, and a buyer taking a house “as is” completes a Temporary Certificate of Compliance request. Commercial resales and new commercial tenants need the same certificate, with the sale or lease agreement attached.
The township’s list of common resale inspection items includes house numbers, working doors and windows, sound decks, porches and stairs, graspable handrails and guards, smoke detectors on every floor and in every bedroom, a carbon monoxide detector, working heat between September 30 and May 30, a sealed flue and a dryer vented outdoors; double-keyed locks are not allowed. The electrical check covers only ground-fault protection, and the township recommends a full independent inspection before moving in. Vacant and foreclosed properties must be registered through Hera Property Registry, the township’s registration partner.
Want this handled start to finish?
Get a free quote →Pennsylvania building code in Bethlehem Township
Ordinance 03-26 brought the township code into line with the UCC’s updated International Codes in February 2026. FEMA’s Community Status Book lists Bethlehem Township (community 420980) as a participating community, with flood maps effective July 16, 2014.
Pennsylvania has one Uniform Construction Code for the whole state, based on the 2021 International Codes since January 1, 2026. Most municipalities enforce it themselves or through a certified third-party agency; where a municipality has opted out, the Department of Labor and Industry handles commercial work and home owners hire a certified agency. Counties do not issue building permits. Pennsylvania rules
Bethlehem Township permit search and official resources
The township has no online permit search; ask Community Development (610-814-6435) about a property’s permits, or file a Right-to-Know request, with copies at 35 cents a sheet. Board of Commissioners minutes are posted by meeting date. The separate City of Bethlehem has its own Bethlehem permit guide.
- Bethlehem Township permits
- Residential construction process
- Commercial construction requirements
- Fee schedule, effective June 1, 2025
- Building permit application
- Forms and documents
- Resale and lease inspection application
- Resale certificate of occupancy procedure
- Zoning and Zoning Hearing Board
- Property maintenance and code enforcement
- Township contacts
- Board of Commissioners minutes
- Pennsylvania L&I municipal UCC elections list
- FEMA Community Status Book, Pennsylvania
Inspections are where schedules slip.
Get a free quote →Bethlehem Township building permit FAQs
Is Bethlehem Township the same as the City of Bethlehem?
No. The township has its own Community Development Department at 4225 Easton Avenue and its own fee schedule.
Do I need an inspection to sell my house?
Yes. Resale, rental and lease of property require an inspection and certificate of occupancy; the application fee is $100.
How much is a permit for a new house?
$0.70 per square foot of gross floor area, at least $1,000, plus the $4.50 UCC fee and Keycodes’ electrical charges.
Do I need a permit to replace my roof?
The township lists reroofing as a construction permit item for commercial buildings only.
Does a shed need a building permit?
Sheds and accessory structures under 1,000 square feet need a zoning permit ($150) rather than a construction permit.
Who inspects electrical work?
Keycodes Inspection Agency, the only third-party agency the township uses for a trade.
How long does plan review take?
Up to 15 business days for a complete residential application and 30 working days for commercial.
Simplify Bethlehem Township permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Pennsylvania. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Bethlehem Township sooner?
Let Alliance prepare, file, and track your Bethlehem Township permits while your crew stays on the job.
More Pennsylvania permitting guides
Palmer Township
Read guide →Lehigh County
Read guide →Lower Macungie Township
Read guide →Bristol Township Building Permit Guide
Read guide →Bucks County Building Permit Guide
Read guide →Butler Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Bethlehem Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.