In the Borough of Hasbrouck Heights, construction permits are issued by the Building Department (Construction & Code Enforcement) at 320 Boulevard, 201-288-2143. Chris Cunningham is both the Construction Official and the Zoning Officer, so site work such as fences, sheds, patios and driveways goes through a zoning review application at the same counter. Inspections are booked by phone and held on Tuesday and Thursday afternoons, and every home sale needs a borough certificate of occupancy: $50 for a one-family house and $75 for a two-family.
What requires a building permit in Hasbrouck Heights?
The borough’s construction FAQ walks through the state categories in plain terms. Ordinary maintenance needs no permit, notice or inspection. Major work, meaning new buildings, additions, alterations and repairs, needs a permit before work begins and usually a zoning approval as well; the borough puts wood decks, swimming pools, hot tubs and sheds in this group. Minor work on one- and two-family homes needs a permit but may proceed after the borough is formally notified; the FAQ lists air conditioners, electrical fixtures, furnaces, HVAC, radon systems, boilers and water heaters. Emergency work can go ahead at once, but the permit application must reach the borough within 72 hours.
Permit needed
- Driveways, fences, retaining walls, sheds, walkways, patios, sidewalks and front steps (zoning review application)
- Pools that can hold 24 inches of water or more, portable or not, plus a pool-compliant fence
- Decks and pools, which add building, plumbing and electrical tech sheets
- Retaining walls 4 feet or taller in total, or shorter walls that affect a foundation
- Egress windows and any window change that needs new framing
- A dumpster placed in the street
No permit, per the borough FAQ
- Roofing and siding replacement on homes
- Same-size window replacement with no framing
- Trimming or removing a tree on private property (curb trees belong to the borough; call Public Works at 201-288-1072)
- A dumpster kept in your own driveway
The borough reprints the state’s ordinary maintenance list on its construction page. It includes painting, wallpaper, interior finishes such as drywall covering less than 25% of the wall area of a one- or two-family home, flooring, cabinets and trim, gutters and screens, same-opening window and door replacement, faucet, trap and same-fixture swaps with no piping changes, and like-for-like switches, receptacles and light fixtures. Cutting away walls or beams, changing exits, and adding, altering or moving pipes or wiring are never maintenance.
What Hasbrouck Heights decides and what the state holds
The permit categories are set by N.J.A.C. 5:23, and the borough says plainly that its job is to enforce those state rules and issue the permits. Local choices are the zoning ordinance (Chapter 275 of the borough code), the combined land use board, the borough’s fees, its resale certificate of occupancy, sign standards for businesses and the street dumpster permit. Every wall, whatever its height, needs zoning approval even when no construction permit is required.
Short on time to read all of this?
Get a free quote →Hasbrouck Heights building department: who handles permitting
The Building Department handles construction permits, zoning review and code enforcement. The Construction Official also serves as Zoning Officer and electrical inspector, and the department also has an Administrative Officer of Land Use. DCA’s roster (September 2, 2026) shows borough officials in the building, plumbing, electrical and fire protection posts, and a private agency, Municipal Inspection Corp, holding the elevator post.
| Detail | Information |
|---|---|
| Building Department | 320 Boulevard, Hasbrouck Heights, NJ 07604 |
| Phone / fax | 201-288-2143 / 201-288-1468 |
| Hours | 9 a.m. to 4:30 p.m. weekdays from Labor Day to Memorial Day; 8 a.m. to 3:30 p.m. from the Tuesday after Memorial Day to the Friday before Labor Day |
| Construction Official and Zoning Officer | Chris Cunningham |
| Elevators | Municipal Inspection Corp (private agency) |
| Borough Hall | 320 Boulevard, 201-288-0195 |
DCA’s roster prints the department’s address as 218-222 Boulevard; the borough’s own page and forms use 320 Boulevard. A construction decision can be appealed to the Bergen County Construction Board of Appeals (201-336-6987).
Hasbrouck Heights permit types
Construction work is filed on the state’s permit application folder with the building, electrical, plumbing and fire technical sections it needs. Site work uses the borough’s Zoning Review Application, revised in November 2024, and businesses use a separate commercial zoning application.
Residential permits
- Driveways, fences, walls, sheds, walkways, patios, sidewalks and steps need the zoning review application with a property survey showing existing and new structures, plan and elevation drawings with dimensions, and the borough’s zoning data table, signed by the owner or a New Jersey engineer, architect or land surveyor.
- Pools and decks need the zoning review application and survey plus building, plumbing and electrical technical sheets. Pool rules are in section 275-21 G of the zoning code.
- Additions and alterations need plans sealed by an architect or engineer, but the Construction Official waives the seal when a homeowner draws the plans for their own single-family home and signs an affidavit, provided the plans are legible and complete. The same exception covers plumbing, electrical and mechanical plans for the owner’s own home.
- Grading. Any soil movement needs a soil movement permit and engineering plans before construction permits are issued, and a two-foot contour topographic plan may be required.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Before signing a lease, a new business files an Application for Zoning Compliance with a $100 fee. Changes to the space need signed and sealed architectural plans with the construction permit folder and the technical sections for the work. Wall signs are allowed only on the wall with the main entrance, no longer than 80% of that wall, no taller than 3 feet, no larger than 45 square feet in total and projecting no more than 6 inches; flashing lights and neon are prohibited, and banners and flags are allowed only for a 14-day grand opening. The commercial zoning compliance form is also required when a commercial building is sold.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the construction permit
- Zoning review. Most projects need the zoning officer’s approval first; the borough posts zone calculators for its R-1 and R-2 one-family zones.
- Planning Board. Under Borough Ordinance 2476 and N.J.S.A. 40:55D-25(c), the Planning Board exercises all the powers of a board of adjustment, so it hears variances as well as site plans. It meets on the first Wednesday of the month from 7 p.m. After a decision is published in The Observer there is a 45-day appeal period, and the land use application says the building permit should be sought after it ends. The board wants an original and 17 copies of the application at least 15 days before the hearing with its fees and escrow, a certified list of owners within 200 feet from the Tax Collector ($10, dated within 60 days) and notices served at least 10 days ahead; for a residential fence, pool, deck, driveway widening or accessory structure, a scaled sketch on a certified survey may be accepted with the board secretary’s approval.
- Soil and county approvals. Projects disturbing more than 5,000 square feet need soil erosion certification from the soil conservation district, and a road opening on a county road needs Bergen County’s permit.
Hasbrouck Heights permit costs and fees
The borough sets its construction fees by ordinance in the Borough Code, which it publishes through eCode360; the Building Department’s page does not list the UCC fee schedule, so call 201-288-2143 for the fee on a specific job. The borough’s own pages and forms do state these charges:
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee or rule |
|---|---|
| Certificate of occupancy on sale, one-family house | $50 |
| Certificate of occupancy on sale, two-family house | $75 |
| Commercial certificate of occupancy | $100 |
| Application for Zoning Compliance (new business) | $100 |
| Dumpster permit for a street placement | $250, normally for no more than 7 days; lights required at night |
| Zoning review application | Fee entered on the form by the office |
The state’s training-fee surcharge is collected in addition to the borough’s construction fees, and the plan review portion is ordinarily paid when the application is filed. Land use board applications carry their own fees and professional escrow, set out in the board’s checklist.
Trade permits and who may pull them
Each trade is a technical section of the same application. Pool and deck applicants, for instance, attach the building, plumbing and electrical sheets to their zoning review. The borough’s inspectors cover building, plumbing and electrical work, and fire inspections are arranged directly with the fire subcode inspector.
- Electrical: electrical fixtures, air conditioners and HVAC units appear on the borough’s list of minor work that may start after notice.
- Plumbing and heating: water heaters, boilers and furnaces are minor work on one- and two-family homes; gas and water piping changes are not maintenance and need a permit.
- Radon systems are also on the minor work list.
- Plans for trades: plumbing plans normally come from a licensed individual or architect, electrical plans likewise, and mechanical plans from a mechanical contractor or architect, unless the homeowner exception applies.
Contractors doing home improvement work must be registered with the state Division of Consumer Affairs, and electrical, plumbing and HVACR contractors need their state licenses; an owner working on their own single-family home can prepare their own plans under the affidavit rule.
Rather not deal with the Hasbrouck Heights Borough building department?
Get a free quote →How to apply for a Hasbrouck Heights building permit
Use the borough’s FAQ to see whether the job is maintenance, minor work, major work or emergency work.
Fill in the zoning review application and data table, attach the survey and drawings, and include the estimated cost.
Variances and site plans are heard on the first Wednesday of the month; wait out the 45-day appeal period.
Add the state application folder, technical sections and sealed plans, or a homeowner affidavit for your own house.
Submit during office hours, which shift earlier in the summer.
Phone 201-288-2143 to book building, plumbing and electrical inspections.
Review, corrections and what causes delay
State rules allow the construction office 20 business days to approve or deny a complete application. Delays in Hasbrouck Heights usually come from earlier steps: a zoning review returned for a missing data table or survey, a soil movement permit and engineering plans that must come first, or a board approval still inside its appeal period.
Inspections and certificates in Hasbrouck Heights
All inspections are by appointment through the Building Department. Building and plumbing inspections are done on Tuesday and Thursday from 2 to 5 p.m., electrical inspections on Tuesday and Thursday from noon to 4 p.m., and fire inspections are scheduled directly with the fire subcode inspector. Minor work and permitted jobs are inspected before they are closed, and new buildings and additions need a certificate of occupancy or approval at the end.
The borough requires a certificate of occupancy when a house or a commercial property is sold. The residential form is picked up at 320 Boulevard and needs buyer and seller details, including the buyer’s phone number; the borough asks for two weeks to process it, and the inspection is carried out by the fire department’s chief. A commercial tenant change or building sale also needs the commercial zoning compliance form.
New Jersey building code in Hasbrouck Heights
Work in Hasbrouck Heights is reviewed against New Jersey’s Uniform Construction Code: the 2024 I-codes and the 2023 NEC became the standard on August 17, 2026, and complete applications under the 2021 codes remain acceptable until February 17, 2027. In FEMA’s Community Status Book, Hasbrouck Heights is community 340041, participating in the National Flood Insurance Program, with flood maps effective August 28, 2019.
New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules
Want this handled start to finish?
Get a free quote →Hasbrouck Heights permit search and official resources
For a printout of open and closed permits on a property, the borough asks for an OPRA request to the Borough Clerk, filed online or in person at Borough Hall; the clerk passes it to the Building Department and usually responds within 7 business days. The borough’s forms page also carries the landlord registration, vacant property registration and fire prevention permit applications, and Planning Board forms are available from the board secretary at 320 Boulevard, 201-288-2143, weekdays from 9 a.m. to 1 p.m. and 2 to 4 p.m.
- Hasbrouck Heights Construction & Code Enforcement
- Zoning review application
- Commercial zoning application
- Soil movement application
- Land use (Planning Board) application
- New business guide
- Borough forms
- OPRA request form
- NJ DCA construction permit forms
- NJ DCA Local Construction Contacts roster
- Bergen County Construction Board of Appeals
- FEMA Community Status Book, New Jersey
Inspections are where schedules slip.
Get a free quote →Hasbrouck Heights building permit FAQs
Do I need a permit to replace my roof or siding in Hasbrouck Heights?
No. The borough says permits are no longer required for roofing and siding on homes.
Do I need a permit for a fence or patio?
Yes. Fences, patios, walkways, driveways, sheds, walls, sidewalks and front steps all need the zoning review application with a survey.
What if I have to do emergency repairs?
Emergency work can start right away, but the permit application must be submitted within 72 hours.
Can I draw my own plans?
For your own single-family home, yes: the Construction Official waives the architect’s seal if you sign an affidavit and the plans are legible and complete.
When are inspections done?
On Tuesday and Thursday afternoons, by appointment at 201-288-2143; fire inspections are booked with the fire inspector.
What does a resale certificate of occupancy cost?
$50 for a one-family house, $75 for a two-family and $100 for commercial property; allow two weeks.
Do I need a permit to take down a tree?
Not for a tree on your own property. A tree by the curb belongs to the borough, so call Public Works at 201-288-1072 instead.
Is there a zoning board of adjustment?
No separate one: the Planning Board exercises the powers of a board of adjustment and meets on the first Wednesday of each month.
Simplify Hasbrouck Heights Borough permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Hasbrouck Heights Borough sooner?
Let Alliance prepare, file, and track your Hasbrouck Heights Borough permits while your crew stays on the job.
More New Jersey permitting guides
Bergen County
Read guide →Hillsdale Borough
Read guide →Little Ferry Borough
Read guide →Hawthorne Borough Building Permit Guide
Read guide →Hillsborough Township Building Permit Guide
Read guide →Hillside Township Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Hasbrouck Heights Borough permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.