Municipal GuideNew JerseyGlassboro Borough · Gloucester County

Glassboro Borough, New Jersey Building Permit Guide

To get a building permit in Glassboro Borough, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Glassboro’s Construction Office in the borough’s Code Enforcement Building, 10 South Poplar Street, issues construction permits, takes a 20% plan review deposit with every application and books inspections through the SDL portal or an e-mailed request form.

Authority: Glassboro Construction OfficePlan review: 20% deposit at filingPhone: 856-881-8140, option 1
Authority
Construction Office10 South Poplar Street
Plan review
20% depositCredited to the final fee
Resale certificate
$100 per houseIncludes one re-inspection
Smoke / CO certificate
$45 to $160Lower fee if early

In the Borough of Glassboro, the Construction Office reviews applications, issues construction permits and inspects residential and commercial work from the Code Enforcement Building at 10 South Poplar Street (856-881-8140, option 1). Jack Eckler is the Construction Official and Building Subcode Official. Since February 5, 2024 every application has needed a non-refundable plan review deposit of 20% of the permit cost, credited to the final fee, and a house sale needs a Resale of Dwelling Certificate plus a smoke, carbon monoxide and fire extinguisher certificate.

What requires a building permit in Glassboro?

The Construction Office makes sure building projects across the borough meet the Uniform Construction Code, and it permits and inspects both residential and commercial work. The borough does not post its own list of exempt jobs, so the state’s rule decides: under the UCC, ordinary maintenance (N.J.A.C. 5:23-2.7) needs no permit, minor work (5:23-2.17A) needs a permit but may begin after the office is notified, and everything else waits for the permit. The forms and checklists the office publishes show the work it sees most:

Residential

  • New houses (with a new construction checklist and a residential certificate of occupancy checklist)
  • Additions and alterations, with building, electrical, plumbing, fire and mechanical sections
  • Decks (residential deck checklist)
  • Pools (residential pool checklist, updated June 2025)
  • Replacing fuel-fired equipment, which needs the chimney verification form
  • Demolition, inspected before backfill and after regrading

Commercial and other

  • New commercial buildings (commercial certificate of occupancy checklist)
  • Tenant fit-outs and changes of use, with sealed architect’s plans showing the use and occupancy load
  • Zoning permits, tree removal and street opening permits through Planning & Zoning
  • Certificates for a change of owner or tenant

What Glassboro decides and what the state holds

The building standards are state law, and Glassboro enforces them unchanged. The borough sets its own fees and deposit rules, runs zoning through its Planning Board and Zoning Board under a 2004 Master Plan reexamined in 2020, and has its own housing rules: a Resale of Dwelling Certificate or Transfer of Title inspection on sale, and a certificate of rental registration from the Chief Housing Officer before a rental is occupied (Borough Code Chapter 379).

Glassboro building department: who handles permitting

The Construction Office is the borough’s enforcing agency, and Planning & Zoning shares the Code Enforcement Building with it. DCA’s roster of local construction officials (as of September 2, 2026) lists the office at Borough Hall, 1 South Main Street, with borough officials in the construction, building, electrical, plumbing and fire protection posts and the Department of Community Affairs as elevator subcode official; DCA therefore handles elevators. The borough’s own page places the office in the Code Enforcement Building on South Poplar Street. The same person is also the construction official in Harrison Township, Gloucester County.

Short on time to read all of this?

Get a free quote →
Glassboro permit contacts
DetailInformation
Construction OfficeCode Enforcement Building, 10 South Poplar Street, Glassboro, NJ 08028
Phone / fax856-881-8140, option 1 / 856-863-4690; Borough Hall 856-881-9230
PaymentsComplete any transaction before the cashier closes at 4:30 p.m.
Construction OfficialJack Eckler (also Building Subcode Official); building inspections Tuesday to Thursday, 12:30 to 3:30 p.m.
Inspection requestsSDL portal, or the request form e-mailed to Construction@glassboro.org
Resale and rental certificatesCode Enforcement Office, 856-881-9230 ext. 88140
Fire preventionBureau of Fire Prevention, 856-881-9230 ext. 88350
ElevatorsNJ Department of Community Affairs

Glassboro permit types

The construction permit is the state UCC application, filed with whichever subcode sections apply: building, electrical, fire protection, mechanical and plumbing, all linked from the Construction page. The office adds its own checklists for new construction, decks and pools, and for the certificate of occupancy on new residential and commercial buildings.

Residential permits

  • New houses. Follow the new construction checklist; a foundation location survey is required at the foundation stage for a new house but not for additions, decks, pools or sheds. Sealed truss drawings must be on site for the framing inspection, and a framing and fire-stopping form (F390) is handed to the inspector.
  • Decks. Open decks over a crawl space or less than 48 inches above the ground need an open-deck inspection of the beams, joists, blocking and hardware before decking.
  • Pools follow the borough’s pool checklist, whose plot plan records the block and lot, the zone, whether the lot is an interior or corner lot, and the front, side and rear yard distances.
  • Heating equipment. Replacing fuel-fired equipment needs the chimney verification form with the permit.

Commercial permits

The new business checklist sets the order. Zoning approval comes first ($50), with the business type, number of employees and hours, and the owner’s signature if the space is leased. A change of owner or tenant with no construction then needs a Commercial Certificate of Transfer of Title/Tenancy ($200 for one unit, $100 for each additional unit). Renovations or a change of use need construction permits with two sets of plans signed and sealed by a New Jersey architect, showing the use and occupancy load; those fees are worked out and given at permit pick-up. The fire prevention application is passed to Gloucester County and costs nothing at filing, a $10 mercantile license comes from the Office of Economic Development, and water and sewer billing details are updated at Borough Hall, 1 South Main Street. Food businesses also need Gloucester County plan approval and a sanitary score, and a borough retail food license.

Not sure this scope needs a permit?

Get a free quote →

What comes before the construction permit

  • Zoning. A zoning permit application to the Zoning Officer at 10 South Poplar Street.
  • Planning Board or Zoning Board. Site plans, subdivisions and zoning adjustment applications; the office also posts its workshop requirements.
  • Gloucester County. Subdivisions and site plans touching county roads or drainage follow the county’s land development rules.
  • Soil erosion. Disturbing more than 5,000 square feet needs certification from the Gloucester County Soil Conservation District, 545 Beckett Road, Swedesboro (856-589-5250).
  • Trees and streets. Borough tree removal and street opening permits.

Glassboro permit costs and fees

Glassboro does not post its construction fee schedule on the Construction page; the fees are set in the borough code and calculated by the office. What the borough does publish is how and when you pay. Since February 5, 2024 every construction permit application needs a plan review deposit when it is submitted, equal to 20% of the total permit application cost and worked out at drop-off. It is deducted from the final permit fee and is not refunded if the permit is abandoned. The rest is paid at pick-up, before the cashier closes at 4:30 p.m., together with the state training surcharge.

Glassboro fees published on borough forms
ItemFee
Plan review deposit20% of the total permit cost at submission, credited to the final fee, non-refundable
Resale of Dwelling Certificate (single unit)$100, including one re-inspection; second re-inspection $35
Transfer of Title application (single unit)$125, including one re-inspection; second re-inspection $35
Smoke, CO and fire extinguisher certificate$45 more than 10 business days before the change of occupant; $90 at 4–10 days; $160 under 4 days
Commercial Certificate of Transfer of Title/Tenancy$200 first unit; $100 each additional unit
Zoning approval for a new business$50
Mercantile license$10

Rather talk it over?

Call 1-855-478-4290 →

Worked example of the deposit rule: if the office prices a permit at $1,000, $200 is due when the application is dropped off and the remaining $800 when the permit is picked up. Booking the fire certificate more than ten business days before closing keeps it at $45 instead of $90 or $160.

Trade permits and who may pull them

Each trade has its own technical section of the construction permit and its own inspection days with the borough’s subcode officials: electrical inspections on Tuesday and Thursday from 10:00 a.m. to 2:00 p.m., fire inspections Monday to Thursday from 7:00 a.m. to noon, and plumbing inspections on Tuesday and Thursday from 8:00 a.m. to noon. Elevators are DCA’s.

  • State licenses. Electrical contractors, master plumbers and HVACR contractors who file trade sections hold New Jersey licenses.
  • Contractors. There is no state general contractor license in New Jersey. Home improvement contractors register with the Division of Consumer Affairs, new-home builders register with DCA, and owners working on their own home are exempt from registration.
  • Tests. Plumbing rough-in is inspected on test (holding pressure, or filled with water 10 feet above the highest drain), and gas piping must hold a pressure test.

How to apply for a Glassboro building permit

1. Settle zoning

File a zoning permit application with Planning & Zoning, or go to the Planning Board or Zoning Board if the plan needs approval.

2. Pick the right forms

Download the UCC construction permit and the subcode sections, and the new construction, deck or pool checklist that fits the job.

3. Prepare plans

Scaled plans, with two signed and sealed sets from a New Jersey architect for commercial fit-outs or changes of use.

4. Drop off and pay the deposit

Submit the package to the Construction Office; the 20% plan review deposit is calculated and paid at drop-off.

5. Track the permit

Create an SDL account to follow the permit online around the clock.

6. Pick up and pay the balance

Collect the permit and pay the remaining fee before 4:30 p.m.; then book inspections.

Rather not deal with the Glassboro Borough building department?

Get a free quote →

Review, corrections and what causes delay

State rules give the office 20 business days to approve or deny a complete application. Plans are checked by the subcode official for each section involved. For a business, the borough’s checklist puts zoning approval first and asks for sealed plans that show the use and occupancy load. Abandoning an application forfeits the deposit, which the office works out from the total permit cost at drop-off.

Inspections and certificates in Glassboro

Request inspections through the borough’s SDL portal (an account is required) or e-mail the construction permit inspection request form to Construction@glassboro.org. An inspection is not scheduled until you receive a confirmation with the appointment date. For one- and two-family houses the borough’s list runs from footing trenches, foundation forms and the foundation before backfill, through underground utilities and slab, to electrical and plumbing rough, gas piping, sill plate, sheathing, framing and fire-stopping, and insulation. Framing is inspected only after the plumbing and electrical rough inspections pass, and all underground electric and plumbing must be approved first. Finals cover fixtures, GFCI receptacles, alarm devices and finished floors, walls and hardware, and the certificate of occupancy follows its checklist.

Other buildings can add inspections of fire suppression and detection systems, heat-producing devices and special inspections, a mid-point check against the barrier-free subcode, and a framing checklist for wood-frame (Type V) buildings in Groups R-2, R-3 and R-4. Buildings over two stories, or jobs with unusual problems, may get extra inspections set by the construction official. A demolition is inspected before the hole is backfilled and again once the lot is back to its original grade.

Selling or renting a home. A Resale of Dwelling Certificate (or the Transfer of Title application) is handled by the Code Enforcement Office by appointment, and all paperwork must be in before the certificate is issued. The smoke alarm, carbon monoxide alarm and fire extinguisher inspection is done at the same visit by the same inspector. The buyer signs a rental acknowledgement, which is required even if the house will not be rented, and a home that becomes a rental needs a certificate of rental registration from the Chief Housing Officer before anyone moves in.

New Jersey building code in Glassboro

Glassboro enforces the statewide UCC through its own Construction Office, with DCA as the elevator agency. FEMA’s Community Status Book lists the Borough of Glassboro (community 340203) as participating in the National Flood Insurance Program, with flood maps effective January 20, 2010; NJDEP flood hazard area approvals can apply in mapped flood areas.

New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules

Want this handled start to finish?

Get a free quote →

Glassboro permit search and official resources

Glassboro uses Spatial Data Logic (SDL) municipal software: residents create an account and log in for round-the-clock permit tracking and inspection requests. For copies of permits, plans or certificates, use the borough’s OPRA record request form from the Municipal Clerk’s page. The borough code book is published on eCode360, and board agendas, minutes, resolutions and ordinances are posted in shared folders linked from the borough website.

Inspections are where schedules slip.

Get a free quote →

Glassboro building permit FAQs

Do I pay anything when I drop off a permit application in Glassboro?

Yes. A plan review deposit of 20% of the permit cost is due at drop-off; it is credited to the final fee and not refunded.

How much is a resale certificate?

$100 for a single-unit dwelling, including one re-inspection, plus the smoke and CO certificate fee.

How much is the smoke and CO certificate?

$45 if you apply more than 10 business days before the change of occupant, $90 at 4 to 10 days and $160 under 4 days.

How do I book an inspection?

Through the SDL portal or by e-mailing the request form; wait for a confirmation with the date.

When does the building inspector inspect?

Building inspections are Tuesday to Thursday, 12:30 to 3:30 p.m.

What does a new business need before opening?

Zoning approval ($50), then a commercial transfer certificate or construction permits, a fire prevention application and a $10 mercantile license.

Does a new house need a foundation survey?

Yes. A foundation location survey is submitted at the foundation inspection for new construction; additions, decks, pools and sheds do not need one.

Who handles elevators?

The New Jersey Department of Community Affairs.

Simplify Glassboro Borough permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Glassboro Borough sooner?

Let Alliance prepare, file, and track your Glassboro Borough permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Glassboro Borough permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.