Woodford County, Kentucky Building Permit Guide

To get a building permit in Woodford County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Versailles-Midway-Woodford County Planning Commission in the county courthouse issues building, zoning, electrical and floodplain permits for the whole county, Versailles and Midway included.

Authority: Versailles-Midway-Woodford County Planning CommissionCode: Kentucky Building and Residential Codes; joint Woodford County Zoning OrdinancePhone: 859-873-8611
Office
103 S. Main St., Suite 204, VersaillesCourthouse; 8 a.m.–4 p.m. weekdays
House permit
$0.20 per sq ftPlus $25 plan review at filing
Plan review
About 2–5 daysOnce the file is complete
Farm exemption
10 acres for a home$50 affidavit; 5 acres for farm buildings

Woodford County has one permit office for every address in the county: the Versailles-Midway-Woodford County Planning Commission, Suite 204 of the courthouse at 103 South Main Street, Versailles (859-873-8611). Its Division of Building Inspection permits houses as well as commercial work, charging $0.20 per square foot for residential construction under the schedule in force since February 13, 2025, and it says a complete residential plan set is usually reviewed in 2 to 5 days.

What requires a building permit in Woodford County?

The joint zoning ordinance makes it unlawful to start building, moving or altering a structure, or to begin or change the use of a property, until the Building Inspector has issued a building permit. Smaller items that do not need a full building permit still need a zoning permit, and grading that changes how a site drains needs a grading permit. The Planning Commission’s permit FAQ gives these examples:

Permit required

  • New homes, duplexes, apartments and commercial buildings
  • Additions, decks, porches and three-season rooms
  • Turning a basement into living space
  • Garages, pole barns and storage sheds, pre-built ones included
  • All swimming pools (in-ground: building permit; above-ground: zoning permit)
  • Installing or replacing a fence (zoning permit above 48 inches)
  • Extending plumbing or electrical systems
  • Moving, enlarging or shrinking door and window openings
  • Filling, excavation, clear-cutting or regrading land
  • Demolition, signs, solar panels and manufactured homes

No permit

  • Repaving an existing driveway or parking area without enlarging it
  • New siding or a new roof
  • Ordinary repairs that are not structural and add no new use
  • Replacing windows or doors with the same size
  • Adding or removing non-load-bearing interior partitions

Houses are covered: the county has a local single-family inspection program, so a new home, an addition or a residential remodel is permitted and inspected locally.

What the county decides and what the state holds

The Fiscal Court and the two city councils adopted one zoning ordinance for the county and both cities, and the Planning Commission sets its own application fees under section 400.3 of that ordinance. The Planning Director serves as the Administrative Official, and the Building Inspector takes final action on building permits and certificates of occupancy. The state keeps plan review and inspection of the larger buildings that the Kentucky Building Code assigns to the Department of Housing, Buildings and Construction, the HVAC permit, the plumbing permit and all trade licenses.

Woodford County building department: who handles permitting

The Planning Commission office, run by Planning Director Steve Hunter, houses both the zoning staff and the Division of Building Inspection. The state’s inspector contact sheet for Woodford County (updated November 14, 2025) lists a local building inspector at the county and names no city as excluded, plus the state building, electrical, HVAC, plumbing and manufactured-housing inspectors who work the county.

Short on time to read all of this?

Get a free quote →
Woodford County permitting contacts
OfficeContact
Versailles-Midway-Woodford County Planning Commission (building, zoning, electrical, grading, floodplain permits; inspections)Woodford County Courthouse, 103 S. Main St., Suite 204, Versailles, KY 40383; 859-873-8611; fax 859-873-6006; 8 a.m. to 4 p.m. weekdays
Woodford County Health Department (septic site evaluation; state plumbing inspector’s desk)229 N. Main St., Versailles; environmental office 859-873-4541; plumbing office hours Tuesday and Thursday, 8 to 9:30 a.m.
Woodford County Road Department (entrances on county roads)160 Beasley Road, Versailles; 859-873-4231; 8 a.m. to 4 p.m. weekdays
Kentucky Transportation Cabinet (entrances on state roads)Local office 859-873-6796; Lexington office 859-246-2355 (numbers printed on the permit checklist)

Cities in Woodford County

Incorporated cities (Census 2025 estimates)
CityBuilding permits and zoning
Versailles (10,734)The same joint Planning Commission office; city water and sewer, 859-873-5436
Midway (1,787)The same joint Planning Commission office; city water, sewer and streets, 859-846-4413

Woodford County permit types

The office posts separate applications for single-family construction; commercial, industrial and multi-family construction; zoning permits; electric permits; demolition; grading; signs; certificates of appropriateness; plats; variances and conditional uses. Applications are filed at Suite 204 with the fee, and the zoning ordinance lets staff take up to five working days to decide whether a file is complete.

Residential permits

A house or addition file holds the signed application, building plans and a site plan drawn to scale with every easement and setback, a copy of the deed or plat, the building permit affidavit, a workers’ compensation certificate, a homeowner’s responsibility acknowledgement where it applies, and, as the job requires, an entrance (access) permit, an electrical permit, a water and sewer certification letter or a health department site evaluation. The square footage you declare must include porches, garages and unfinished areas, and basements count toward the fee. An energy code report is optional. The building permit affidavit binds the builder to repair any sidewalk, grading or stormwater work in the subdivision that the job disturbs before a certificate of occupancy is issued.

Commercial permits

Buildings other than one- and two-family homes need a site plan showing access, parking and loading, refuse areas, water and sewer service sizes, screening, sign locations, health department sign-off, stormwater design and whether the site lies in the floodplain. New development usually needs a site development plan approved by the Planning Commission after its Technical Review Committee, and the buildings that fall under state jurisdiction also go to the Department of Housing, Buildings and Construction for plan review.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. Variances and conditional uses go to the Board of Adjustments; zone changes go to the Planning Commission and then the legislative body. Applications must be filed at least 21 days before the hearing.
  • Agricultural land. Certain conditional uses in the Agricultural and Conservation districts first go to the Agricultural Advisory Review Committee.
  • Plats. Minor and major subdivision plats pass the Technical Review Committee before final approval.
  • Septic or sewer. A health department site evaluation, or a water and sewer letter from Versailles, Midway or the serving utility.
  • Road access. An entrance permit from the city, the county Road Department or the Kentucky Transportation Cabinet, depending on who owns the road.
  • Floodplain. A floodplain development permit and an elevation certificate; the building or zoning permit is held until the floodplain permit is approved.
  • Historic overlay. Projects on property in a Historic Overlay district go to the Board of Architectural Review for a certificate of appropriateness.

Woodford County permit costs and fees

The fees below come from the Planning Commission’s fee schedule effective February 13, 2025. The $25 plan review fee is paid when the application is filed; the building permit fee is set from the square footage.

Building, zoning and other permits (schedule effective February 13, 2025)
PermitFee
New house, residential addition (decks included), detached garage or carport, accessory building over 200 sq ft, residential remodel$0.20 per sq ft
Duplex, townhouse or apartment units$0.20 per sq ft, $250 minimum
Commercial or non-residential construction, remodel or addition$0.25 per sq ft, $250 minimum
Industrial buildings, warehouses and self-storage$0.25 per sq ft, $50,000 maximum
In-ground pool / commercial range hood$100 each
Zoning permit: fence over 48 in., shed of 200 sq ft or less, above-ground pool, small detached deck$30
Temporary use permit$50
Farmstead residential exemption (10+ acres) / agricultural building exemption (5+ acres)$50 / $20
Building permit plan review$25
180-day extension of a voided permit$50
Sprinkler system or fire alarm$200
Manufactured or mobile home$100
Demolition$50
Grading or floodplain development permit$75
Solar panels$10 per panel
Electrical permit$10
Building under state (HBC) jurisdictionPermit to build fee $0.10 per sq ft, $25,000 maximum
Work started without a permitDouble fees may be charged

Rather talk it over?

Call 1-855-478-4290 →

Worked example. A new house with 2,400 square feet across all floors, counting the attached garage, porches and basement, costs 2,400 × $0.20 = $480 for the building permit, plus the $25 plan review fee paid at filing, for $505. The electrician’s $10 electrical permit and the state plumbing and HVAC permits are separate.

Planning fees in the same schedule include variances and conditional use permits at $300 each, administrative appeals $100, minor subdivision plats $295, major plats and site development plans $595, zone changes from $325 to $595 by district, and certificates of appropriateness $75 before the board or $25 when staff can approve them.

⚠️ Fee revision pending. The Planning Commission’s November 12, 2026 agenda lists a draft fee schedule revision for January 1, 2027. Until a new schedule is adopted and posted, the February 13, 2025 figures apply.

Trade permits and who may pull them

  • Electrical. The Planning Commission sells the electric permit for $10; the form asks for the electrician’s master and contractor license numbers. The work is inspected by the local electrical inspector named on the residential acknowledgement, and the permit holder usually books it. The office’s FAQ says a licensed electrician or the homeowner may do the work.
  • Plumbing. The state plumbing inspector issues and inspects plumbing permits, keeping office hours at the Woodford County Health Department on Tuesdays and Thursdays from 8 to 9:30 a.m. The state’s plumbing division issues permits to licensed master plumbers and to homeowners for plumbing in their own residence; the Planning Commission’s permit FAQ says only a licensed plumber may do the work, so a homeowner should confirm with the state inspector first. State house fees: $50 plus $14 per opening.
  • HVAC. Every installation or replacement needs a state HVAC permit, bought through the state’s SmartGov portal by a licensed or authorized person, and a state mechanical inspection.
  • Fire protection. Sprinkler and fire alarm systems carry a $200 local permit.
  • Licenses. The checklist asks for a business license registered with the city and/or county where one applies. Electricians, plumbers and HVAC contractors hold state licenses.

Rather not deal with the Woodford County building department?

Get a free quote →

How to apply for a Woodford County building permit

1. Check zoning and the floodplain

Call 859-873-8611 with the address to confirm the district, setbacks and whether the lot is in a flood zone.

2. Arrange water and sewer

Get a septic site evaluation from the health department or a certification letter from the city utility.

3. Get entrance approval

From the county Road Department, the city or the state, depending on the road.

4. Draw plans

Building plans and a site plan to scale with easements and setbacks.

5. File at Suite 204

Application, checklist items, affidavit and the $25 plan review fee.

6. Pay and post the permit

Pay the square-foot fee on approval and keep the permit on site.

7. Line up the trades

Electrical permit from the same office; plumbing and HVAC from the state.

Review, corrections and what causes delay

A complete residential file with no technical problems is normally reviewed in about 2 to 5 days, and the office says most permits are processed within a week. Delays come from a missing site evaluation, a site plan without easements, a missing workers’ compensation certificate, a floodplain permit that has not yet been approved, or a project that first needs a variance, conditional use or development plan with a public hearing. Work that starts without a permit can draw a stop-work order and double fees.

Inspections in Woodford County

Call the Planning Commission at 859-873-8611 to schedule residential building inspections. The residential acknowledgement lists the stages: footing, slab, poured wall, framing, fire wall, insulation, rough-in and final plumbing, rough-in and final HVAC, rough-in, bonding and final electrical, and a final building inspection. Additions and remodels must bring smoke and carbon monoxide alarms up to date throughout the house, and pools need a 4-foot barrier with self-closing, self-latching gates.

No new or altered building may be used until the Building Inspector issues a certificate of occupancy (or a final approval or certificate of completion for an addition, deck or remodel). The office’s FAQ says a permit stays active only with at least one inspection in every 180 days; the acknowledgement adds that work must start within 90 days and finish within one year, with one six-month extension available on written request.

Kentucky building code in Woodford County

FEMA’s Community Status Book lists Woodford County as a participant in the National Flood Insurance Program, on a flood map effective December 21, 2017. The flood article of the zoning ordinance requires the lowest floor of a new or substantially improved home, basement, mechanical equipment and ductwork included, to sit at least 1 foot above the base flood elevation, certified by an engineer or surveyor. After the April 2025 flood the Fiscal Court authorized a recovery buyout program on September 23, 2025.

Kentucky has one mandatory statewide building code that local governments may not add to. Cities and counties enforce it and run zoning. The state reviews plans for larger and higher-risk buildings, and the local program reviews smaller ones. Kentucky rules

Want this handled start to finish?

Get a free quote →

Permit search and official resources

Permit files are kept by the Planning Commission office; it posts its own open records request form, and its meeting agendas, livestreams and archived minutes are linked from its website.

Inspections are where schedules slip.

Get a free quote →

Woodford County permit FAQs

Who issues building permits in Woodford County?

The Versailles-Midway-Woodford County Planning Commission, Suite 204 of the courthouse, 103 South Main Street, Versailles; 859-873-8611. It covers the unincorporated county, Versailles and Midway.

How much does a permit for a new house cost?

$0.20 per square foot, counting garages, porches, unfinished areas and basements, plus a $25 plan review fee.

Do I need a permit for a fence or shed?

A fence over 48 inches and a shed of 200 square feet or less need a $30 zoning permit; a shed over 200 square feet needs a building permit at $0.20 per square foot.

Can a farm house skip the building permit?

Yes, if the farm is registered with the PVA, the house sits on at least 10 acres outside city limits and the owner files the farmstead affidavit ($50). Farm buildings qualify on 5 acres ($20).

How long does review take?

About 2 to 5 days for a complete residential application.

Can I do my own wiring?

The office’s FAQ says a homeowner may do electrical work; the $10 electrical permit is still required.

Who handles septic systems?

The Woodford County Health Department, 229 North Main Street, Versailles (859-873-4541).

Will the permit fees change in 2027?

A draft revision effective January 1, 2027 is on the Planning Commission’s November 12, 2026 agenda; it is not adopted yet.

Simplify Woodford County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Kentucky. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Woodford County sooner?

Let Alliance prepare, file, and track your Woodford County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Woodford County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.