Paducah, Kentucky Building Permit Guide

To get a building permit in Paducah, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Paducah’s Community Development Department, Building Division, on the first floor of City Hall issues building, electrical and HVAC permits inside the city through the Online Services Portal.

Authority: Community Development Department, Building DivisionFiling: Online Services PortalPhone: 270-444-8527
Building Division
300 South 5th StreetCity Hall, 1st floor, 270-444-8527
Apply
Online Services PortalAccount required, open 24 hours
Plan check
A few days to 30 daysDepends on size and type
Floodplain permit
$100 applicationCity Engineer is administrator

Inside the City of Paducah, permits come from the Building Division of the Community Development Department, City Hall, 300 South 5th Street (270-444-8527), and are applied for and paid through the city’s Online Services Portal. The city created the department in 2026, moving building and electrical inspection out of the Fire Prevention Division. Plan check takes from a few days to 30 days, every new house needs a certificate of occupancy, and land in McCracken County outside the city goes to the county’s own inspection department instead.

What requires a building permit in Paducah?

Paducah’s rule is broad: apart from cosmetic finishes, every new building, addition and renovation needs a permit, residential or commercial. The Building Division’s permit page then spells out the common cases.

Permit required

  • Detached garages, sheds, carports, pergolas, arbors, gazebos, decks and pools; for sheds and similar accessory buildings the threshold is over 200 sq ft at a home and over 120 sq ft at a business
  • Residential fences in every zone; commercial fences only over 8 ft
  • Awnings, except small window awnings on houses
  • All electrical work beyond normal maintenance
  • New and replacement HVAC units
  • Placement of manufactured homes, with their foundations, decks and porches
  • Every sign, including a face change-out
  • Tents and temporary structures over 120 sq ft
  • Demolition, except residential accessory structures

No permit

  • Cosmetic finishes
  • Residential above-ground pools (a 48-inch barrier is still required unless the pool wall is 48 in tall with a removable or lockable ladder)
  • Window awnings on one- and two-family homes that project no more than 54 in and need no extra support
  • Commercial fences 8 ft or lower (zoning setbacks still apply)

Accessory buildings must meet the zone’s side and rear setbacks and may not be taller or larger than the house or main building. Manufactured homes are allowed for single-family use in the R-2, R-3 and R-4 districts. An in-ground pool needs building and electrical permits, a fence permit if no enclosure exists, and a plumbing permit to discharge waste water. The permit page still says demolition permits come from the Fire Prevention Division; since the 2026 reorganization, ask the Building Division where to file.

What the city decides and what the state holds

The city enforces the 2018 Kentucky Building Code and Kentucky Residential Code, splitting the work with the state Department of Housing, Buildings and Construction (HBC) under section 104 of the building code: the Building Division reviews and inspects what the code leaves local, and HBC takes the buildings it reserves. HBC also approves the site placement of factory-built Kentucky Industrialized Buildings. Zoning, site plans, historic review, flood rules and right-of-way work are the city’s own.

Short on time to read all of this?

Get a free quote →

Paducah building department: who handles permitting

On August 25, 2026 the mayor announced a Department of Community Development combining the Planning Department with code enforcement and the building and electrical inspection services that had sat in the Fire Prevention Division; Carol Gault, the planning director, heads it. The city’s downloadable permitting guide still sends applicants to the Fire Prevention Division at the same 270-444-8527 number. HBC’s McCracken County contact sheet, last updated July 19, 2024, lists the City of Paducah as the local building and HVAC inspector at 300 South 5th Street, and the McCracken County inspector for the rest of the county, excluding Paducah.

Paducah permitting contacts
OfficeContact
Building Division (building, electrical, HVAC permits; inspections)City Hall, 1st floor, 300 South 5th Street, Paducah, KY 42003; 270-444-8527
Planning Division (zoning, site plans, boards)City Hall, 300 South 5th Street; 270-444-8690; planninginfo@paducahky.gov
Development Liaison (kick-start meetings, project status)270-444-8604; development@paducahky.gov
Engineering Department (floodplain administrator, stormwater, right of way)City Hall, 2nd floor; 270-444-8511
Fire Prevention Division (fire code inspections)Fire Station No. 1, 301 Washington Street; 270-444-8522
McCracken County Health Department (state plumbing inspector’s office)916 Kentucky Avenue; 270-444-9631 ext. 157; Monday, Wednesday and Thursday, 8 to 9 a.m. Central
KYTC District 1 permits (state highways)5501 Kentucky Dam Road, Paducah; 502-764-0645

Outside the city limits, McCracken County’s inspection department handles permits; the Building Division can confirm whether an address is inside the city.

Paducah permit types

Paducah files permits through its Online Services Portal, a 24-hour system that needs a free account. From it you apply for residential and commercial building permits and for plans, rezonings, subdivisions and sign permits, upload documents, follow reviews, see inspection results and pay invoices, fines and liens. The city’s Scope My Project tool asks questions about a project and returns a summary of zoning rules, permits, licenses and an estimated permit fee.

Residential permits

House permits are filed under “Apply for Permit”. Work that does not change a home’s layout or size may not need drawings or a site plan. An owner working on their own home completes the city’s Homeowner’s Affidavit instead of the contractor paperwork. Short-term rentals are a zoning question first: in R-1 only special-event rentals of up to seven days, two weeks a year, are allowed; R-2, R-3, POP and NSZ need a conditional use permit; R-4 and denser zones allow them by right.

Commercial permits

Every commercial, industrial and multi-family development, parking lot and addition needs an approved site plan before any permit issues. Staff recommend a kick-start meeting with the Development Liaison and staff from each department first. The site plan, drawn to the city’s checklist, is filed under “Apply for Plans” and reviewed by Planning, Engineering and, where it applies, Fire Prevention. No new business may open before it has a certificate of occupancy and a city business license.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Boards. Variances, conditional uses and non-conforming use changes go to the Board of Adjustment (last Monday, 5:30 p.m.); zone changes, major subdivisions, planned unit developments and certificates of site approval go to the Planning Commission (first Monday, 5:30 p.m.). Applications are due the Friday 21 days before the meeting.
  • Historic and neighborhood zones. Exterior changes visible from a public right of way in the H-1 and H-2 zones need a Certificate of Appropriateness, and exterior changes in the Neighborhood Services Zone a Certificate of Zoning Compliance, both from the Historic and Architectural Review Commission (second Monday, 5:30 p.m.). Razing a building in the Demolition Control Zone needs a demolition control permit, decided within 30 days.
  • Stormwater. A stormwater management plan is required when a project disturbs an acre or more, is part of a larger common plan, or is a non-residential development with 10,000 sq ft or more paved and under roof; disturbing an acre or more also needs an erosion prevention and sediment control permit from Engineering.
  • Floodplain. Any development in a special flood hazard area needs the city’s development permit before work starts.
  • Right of way. A new driveway or curb cut on a city street needs an Engineering right-of-way permit with insurance and a bond; state highways need a KYTC District 1 permit.

Paducah permit fees

The city says some permit fees are fixed and others are based on the value of the construction, and the portal invoices them; the plan check fee is paid when plans are submitted. The building fee schedule itself sits in the Paducah Code of Ordinances, with the zoning and planning fees in section 126-143, and is not reproduced on the city’s pages. Ask the Building Division for a quote, or use Scope My Project for an estimate. The fees the city does print:

Fees published on Paducah’s pages
ItemFee
Demolition permit$50
Minor site plan (no stormwater or erosion plan)$50, non-refundable
Full site plan (with stormwater or erosion plan)$100, non-refundable
Special flood hazard area development permit$100 application fee
Building, electrical and HVAC permits; plan checkCode of Ordinances schedule; invoiced through the portal
Right-of-way permitBond set by the City Engineer; $1,000,000 / $1,000,000 / $500,000 insurance
State plumbing permit, one- or two-family home$50 plus $14 per opening (HBC)
State plumbing permit, commercial$50 plus $20 per opening (HBC)

Rather talk it over?

Call 1-855-478-4290 →

Trade permits and who may pull them

  • Electrical. The Building Division issues and inspects electrical permits; give the electrician’s CE and ME license numbers. Work must be done by a licensed electrical contractor employing a licensed master electrician, but a homeowner working on their primary residence is exempt from the licensing requirement. Finished electrical work receives a Certificate of Compliance.
  • HVAC. Paducah is one of the local HVAC jurisdictions on HBC’s list, so the city issues HVAC permits. HVAC has its own application, completed by a master HVAC license holder; homeowners are exempt from licensing on their primary residence when replacing like for like in the same place, and only licensed contractors may work on commercial systems.
  • Plumbing. Plumbing permits and inspections are HBC’s; the state inspector keeps office hours at the McCracken County Health Department. HBC issues permits to licensed master plumbers or to homeowners plumbing their own residence.
  • Contractors. Every contractor and subcontractor needs a Paducah business license, and the general contractor must carry workers’ compensation or file a waiver affidavit if it has no employees.

How to apply for a Paducah building permit

1. Check the address and zone

Confirm the site is inside city limits, that the address matches city records and that there are no liens or fines; check the zone on the city map.

2. Book a kick-start meeting

For larger projects, through the Development Liaison (270-444-8604).

3. Get the site plan approved

Commercial, industrial, multi-family and parking projects file under “Apply for Plans” with the $50 or $100 fee.

4. Clear flood, stormwater and board items

Engineering permits, and Board of Adjustment, HARC or Planning Commission approvals where needed.

5. Apply for the permits

Building, electrical and HVAC applications in the portal, with drawings, license numbers and insurance proof.

6. Pay and start work

Once corrections are cleared and fees are paid, the permits issue.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

Complex projects go through plan check, which takes from a few days to 30 days depending on size and type; simpler ones go straight to clerical review. That review checks contractor business licenses, workers’ compensation, state licenses, the stated construction value, unpaid city payroll taxes, liens or fines on the property and the address. Drawings that need changes come back with a corrections list. Missing a board deadline (21 days before the meeting) or skipping the site plan are the usual causes of delay.

Inspections in Paducah

Book inspections through the portal or by calling the Building Division at 270-444-8527 (the web version of the permitting guide gives the department’s 270-444-8690), at least 24 hours ahead; there is no need to ask for a particular inspector. Have the permit number, address, project type and inspection type ready, and have someone on site.

Building inspections
StageWhen
FootingBefore concrete, to check depth, soil, location and reinforcement
FoundationBefore concrete or backfilling cells
Rough frameBefore wall finishes; framing, mechanical, plumbing, electrical and gas
FinalBefore occupancy; all trade finals and life safety

Every new house, one- and two-family included, needs a final inspection and a certificate of occupancy before anyone moves in, and so does every new business. A change of use needs a new certificate; a change of owner alone does not. Appeals from the inspectors’ decisions go to the Building, Electrical, and Fire Codes Appeals Board.

Kentucky building code

Alongside the state codes, the Building Division works under chapters 18 (building regulations), 42 (environment, including rental occupancy permits) and 46 (fire prevention) of the Paducah Code. The flood damage prevention ordinance and current flood maps were adopted in November 2011; FEMA’s Community Status Book lists Paducah as participating in the National Flood Insurance Program on a map dated November 2, 2011. The City Engineer is the floodplain administrator, and a flood permit needs plans by a Kentucky-registered engineer or architect and a FEMA elevation certificate. The 12.25-mile floodwall protects about 11,000 acres. The City Commission’s November 10, 2026 agenda carries an ordinance renaming the street-cut rules “Right of Way Encroachments” and extending them to temporary closures and equipment in a public way.

Kentucky has one mandatory statewide building code that local governments may not add to. Cities and counties enforce it and run zoning. The state reviews plans for larger and higher-risk buildings, and the local program reviews smaller ones. Kentucky rules

Want this handled start to finish?

Get a free quote →

Paducah permit search and official resources

Permit, plan, inspection and code-case records can be looked up in the Online Services Portal. Commission agendas and minutes are on the city clerk’s meeting page.

Inspections are where schedules slip.

Get a free quote →

Paducah permit FAQs

Who issues building permits in Paducah?

The Building Division of the Community Development Department, City Hall first floor, 270-444-8527. McCracken County handles land outside the city.

Do I need a permit for a shed or fence in Paducah?

A residential shed or accessory building needs one above 200 sq ft, and every residential fence needs one. Commercial fences need one only above 8 ft.

How long does plan review take?

From a few days to 30 days for the initial review, depending on size and project type.

Can a homeowner do their own electrical or HVAC work?

On a primary residence, yes: homeowners are exempt from the licensing requirement, though a permit is still needed. For HVAC the exemption covers like-for-like replacement in the same location.

Does a new house need a certificate of occupancy?

Yes. All new homes, including one- and two-family dwellings, need a final inspection and certificate before use.

How much is a demolition permit?

$50, for any building except residential accessory structures.

What if my lot is in a flood zone?

File a special flood hazard area development permit with Engineering ($100) before any work, with engineered plans and an elevation certificate.

Simplify Paducah permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Kentucky. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Paducah sooner?

Let Alliance prepare, file, and track your Paducah permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Paducah permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.