Skip to main content
Municipal GuideKentuckyBarren County · Kentucky

Barren County, Kentucky Building Permit Guide

To get a building permit in Barren County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

One office in Glasgow, the City of Glasgow Building and Electrical Inspectors Office, issues building, electrical, sign and demolition permits for rural Barren County as well as the city.

Authority: City of Glasgow Building and Electrical Inspectors OfficeCode: Kentucky Building and Residential Codes (County Ordinance 352)Phone: 270-651-3921
Permit office
200 South Green St., Suite 200Glasgow; serves the county and its 3 cities
New house fee
$350–$500 buildingBy floor area, plus $25 plan review
Inspections
Call by 9:00 a.m.Same-day visit, 5 days a week
County zoning
Approved by commissionOct. 19, 2026; Fiscal Court next

In Barren County the building inspector’s office is shared: the City of Glasgow Building and Electrical Inspectors Office at 200 South Green Street, Suite 200 (270-651-3921) issues building, electrical, sign and demolition permits for the unincorporated county as well as Glasgow, under a county building inspection program set up by Ordinance 352. A new single-family house carries a flat building fee of $350 to $500 by floor area, and inspections called in before 9:00 a.m. are done the same day.

What requires a building permit in Barren County?

Barren County is one of the Kentucky counties that permits houses. Fiscal Court Ordinance 352 adopted the state building code, including the one- and two-family dwelling code, and established a county building inspection program run by a certified appointee, so a house in the countryside goes through plan review and inspections much as one in town does. The office’s fee schedule shows what it permits in practice:

Permit needed

  • New houses, duplexes and their additions or alterations
  • Detached garages and pole barns that are not farm-exempt
  • Storage buildings and sheds over 200 sq ft
  • Decks that are covered or more than 30 inches high
  • In-ground and partly in-ground swimming pools
  • Fences over 7 feet tall
  • Roof-mounted solar, signs 15 feet or taller, cell towers
  • Single-wide, double-wide and modular homes
  • Multi-family, commercial and industrial buildings

Exempt or different route

  • Farm buildings used only for agriculture on 10 acres or more (never a dwelling)
  • Sheds of 200 sq ft or less, uncovered decks up to 30 inches
  • Fences 7 feet or lower
  • Projects in the state’s jurisdiction: the county issues a $150 permit only after the state approval letter
  • Septic systems (county health department)

The office points applicants to the Kentucky Residential Code’s own list of work that needs no permit. Pole barns have a firm line: anything wider than 48 feet, or built for commercial use, needs plans stamped by a licensed engineer, and a pole building meant to be lived in (a “barndo”) must meet the entire residential code.

What the county decides and what the state holds

The county side covers house plan review and inspections, electrical inspection by a certified inspector the county approves, permits for manufactured homes (Ordinance 360 bars setting up any mobile or manufactured home without one) and enforcement of the property maintenance code through a five-member board. The Joint City-County Planning Commission writes the land rules. The state keeps plan review and inspection of the larger buildings that fall in its jurisdiction, and it issues and inspects every plumbing permit.

Barren County building department: who handles permitting

The county’s own building page names the City of Glasgow Building and Electrical Inspectors Office as the office for both Glasgow and Barren County. The department’s county contact sheet (Department of Housing, Buildings and Construction) agrees: it lists one local building inspector whose area includes Cave City, Glasgow and Park City, and it lists the state electrical, HVAC and plumbing inspectors assigned here.

Short on time to read all of this?

Get a free quote →
Barren County permitting contacts
OfficeContact
City of Glasgow Building and Electrical Inspectors Office (building, electrical, sign, demolition)200 South Green St., Suite 200, Glasgow, KY 42142-0278; 270-651-3921; fax 270-651-9555; permit portal on Cloudpermit
Joint City-County Planning Commission (subdivision, setbacks, floodplain)200 S. Green St., Suite 201, Glasgow, KY 42141; 270-659-0661; 7:30 a.m. to 4:30 p.m., Monday to Friday
BITS office (new addresses)270-651-2145
Barren County Health Department (septic; state plumbing inspector’s office hours)200 S. Green St., Glasgow, KY 42141; 270-651-8321 (Environmental, option 3); plumbing desk ext. 451, Tuesday and Friday 8:00 to 9:30 a.m. Central
County Road Department / state road office (entrances, culverts)270-678-2832 / 270-746-7898
Barren County Judge/Executive117 North Public Square, Suite 3A, Glasgow, KY 42141; 270-651-3338

Cities in Barren County

Incorporated cities (Census 2025 estimates)
CityBuilding permits
Glasgow (15,302)Same Glasgow office; city zoning code; flood program participant
Cave City (2,398)Covered by the same local inspector, per the state sheet; own zoning ordinance through the joint commission
Park City (629)Covered by the same local inspector, per the state sheet; own zoning ordinance through the joint commission

Barren County permit types

The office posts separate checklists for work under the Kentucky Residential Code and the Kentucky Building Code, a manufactured home checklist and examples for tiny homes, pole barns and pools, and it takes applications through its Cloudpermit portal or at the Green Street counter.

Residential permits

A house file starts with an address from the BITS office and a plot plan drawn by a licensed surveyor showing the building behind the setbacks; a plat copied from the clerk’s office will not do. The plot plan can be waived when the parcel is at least 10 acres, was split off before 1978 and never changed, or is a single parcel over 2 acres where the house will sit at least double the setbacks (usually 70 feet from the road right-of-way, 20 feet from the sides and 40 feet from the rear) and the owner signs a waiver. Plans need not be professionally drawn, but they must show a dimensioned floor plan, door and window sizes, hall and stair widths, room uses and the rafter or truss direction; truss and engineered-lumber spec sheets must be in before the framing inspection. The owner or contractor also signs the office’s minimum requirements statement.

For a manufactured home the checklist asks for the installer’s certified-install (C-I) number and, for a used home, the state B-1 seal number before the electrical inspection, and the home must be underpinned within 60 days of the permit.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Multi-family, commercial and industrial buildings are priced by area and carry a $285 plan review fee ($385 for assembly buildings over 10,000 sq ft). Where the building is large enough to fall in the state’s plan review jurisdiction, the applicant first gets the state approval letter, then pays the county $150 for its permit.

What comes before the building permit

  • Address. From the BITS office, 270-651-2145.
  • Septic release or sewer proof. The health department’s site evaluation and permit, or proof of sanitary sewer.
  • Subdivision. Splitting land goes through the joint planning commission: minor plats of five lots or fewer with no new street are approved by staff, larger ones by the commission.
  • Entrance and culvert. Approval from the county road department, or from the Kentucky Transportation Cabinet on a state highway.
  • Floodplain. Questions go to the commission’s local floodplain manager at 270-659-0661.
⚠️ County zoning is pending. Unincorporated Barren County has had no zoning ordinance, only subdivision rules. On October 19, 2026 the Joint City-County Planning Commission approved the text of a proposed Barren County Zoning Ordinance (including an article on high-intensity technological infrastructure), an official zoning map and a fee schedule for it. The Planning Director told that hearing that before the ordinance can be implemented the Fiscal Court must create a board of adjustment and appoint its members.

Barren County permit costs and fees

The fee schedule posted on the county’s building inspector page covers building, HVAC and electrical inspections; it prints no adoption date, and every permit on it is valid for 180 days after issuance. House building fees are flat amounts by floor area, and the electrical fee is added on top.

Rather talk it over?

Call 1-855-478-4290 →
Building, electrical and HVAC fees (county building inspector page)
ItemFee
New single-family house: to 2,000 / 2,001–3,000 / 3,001–4,000 / over 4,000 sq ft$350 / $400 / $450 / $500
House addition or alteration, same bands$175 / $200 / $225 / $250
New two-family dwelling, same bands$525 / $600 / $675 / $750
Residential plan review$25
Electrical: new house / addition / duplex$200 / $100 / $300
Residential HVAC$130 first system, $75 each additional
Multi-family, commercial, industrial new construction15 cents per sq ft, minimum $475
Commercial plan review$285 ($385 assembly over 10,000 sq ft)
Commercial electrical1.25% of the electrical contract, minimum $285
Single-wide / double-wide / modular home$100 / $200 / $300
Detached garage or pole barn$150 building + $75 electrical
In-ground pool$125 building + $100 electrical + $25 plan review
Shed over 200 sq ft$75 building + $75 electrical
Fence over 7 ft / deck covered or over 30 in$75 / $100
State-jurisdiction building (approval letter needed)$150
Re-inspection, consultation, one-trip electrical$75 each
Service reconnect inspection$75

The schedule’s first band is printed as “> 2000”; read with the bands that follow it, it covers houses up to 2,000 sq ft. The manufactured home checklist lists the modular home fee as $250 while the fee schedule says $300, so ask which applies.

Worked example. A new 2,400 sq ft house with one HVAC system: $400 building + $25 plan review + $200 electrical + $130 HVAC = $755 to the Glasgow office, before the state plumbing permit and the health department’s septic fees.

Septic fees are set by the Barren River District Health Department: $230 for the site evaluation and $315 for the construction permit. The planning commission charges separately for its reviews: $300 for a variance or appeal, $350 for a conditional use, $500 for a zone change, $150 plus $25 a lot for a minor subdivision plat and $450 plus $5 an acre for a development plan.

Trade permits and who may pull them

  • Electrical. Pulled at the Glasgow office with the building permit. An owner who lives, or will live, at the address may do the wiring; a landlord or renter may not. If a state-licensed electrician does the work, the electrician must sign off on that part of the permit in person at the office. A building whose power has been off for a year or more needs a $75 service reconnect inspection, with an owner affidavit, before the utility will reconnect it.
  • HVAC. HVAC fees are on the Glasgow office’s schedule ($130 for a home’s first system, $75 for each extra) and its page lists HVAC inspectors on staff. The state HVAC division, which has required a permit for all new construction since 2011 and sells it only to licensed or authorized people, also keeps an inspector assigned to the county, so ask the office which permit your job needs.
  • Plumbing. A state permit and a state inspector, who keeps office hours at the health department on Tuesdays and Fridays from 8:00 to 9:30 a.m. Central (270-651-8321, ext. 451). State fees for a one- or two-family job are $50 plus $14 per opening; a homeowner can get a permit for a home they occupy or are building for themselves, with an affidavit.
  • Contractors. Electricians, plumbers and HVAC contractors hold state licenses; the county’s pages list no local contractor license.

Rather not deal with the Barren County building department?

Get a free quote →

How to apply for a Barren County building permit

1. Get the address

Ask the BITS office for an address if the lot has none.

2. Settle sewage

Get the health department’s septic release, or proof of sewer service.

3. Order the plot plan

Hire a licensed surveyor, or qualify for and sign the waiver.

4. Clear the entrance

Have the road department approve the entrance and culvert size.

5. Assemble plans

Floor plan, window and door sizes, stair and hall widths, truss specs.

6. File and pay

Apply on the Cloudpermit portal or at Suite 200, sign the minimum requirements statement and pay.

7. Add the trades

Your electrician signs in at the office, the plumber buys the state plumbing permit, and the office says where the HVAC permit comes from.

Review, corrections and what causes delay

The office’s plan reviewer checks the drawings against the Kentucky Residential or Building Code. The usual holdups are a missing plot plan (a clerk’s plat is not accepted), no septic release, truss specs that have not been turned in (the framing inspection waits for them) and an electrician who has not come in to sign.

Inspections in Barren County

Inspectors work five days a week, holidays excepted. Call 270-651-3921 to book: a request made before 9:00 a.m. Central is inspected the same day, and later calls are not guaranteed that day. Each inspection must be requested by the permit holder or an agent.

Footings are a frequent check. The office’s standard is 24 inches from finished grade to the bottom of the footing, at least 18 inches wide and 8 inches of concrete, with two continuous rows of #4 rebar on chairs. The framing inspection follows once truss specs are on file, and a pool receives its certificate of completion only after the code’s barrier rules are met. A failed inspection costs $75 to re-inspect.

Kentucky building code in Barren County

Barren County enforces the statewide codes through Ordinance 352. FEMA’s Community Status Book lists the county as a participant in the National Flood Insurance Program on a flood map effective May 3, 2011, with a Community Rating System class 9 rating that gives policyholders a 5% discount; Glasgow participates separately.

Want this handled start to finish?

Get a free quote →

Kentucky has one mandatory statewide building code that local governments may not add to. Cities and counties enforce it and run zoning. The state reviews plans for larger and higher-risk buildings, and the local program reviews smaller ones. Kentucky rules

Permit search and official resources

Permit records sit with the Glasgow office and its Cloudpermit portal; call 270-651-3921 for a permit’s status. For older or formal records, the Fiscal Court posts its own open records policy and a request form on the county document page. Zoning maps, subdivision files and planning minutes are on the joint planning commission’s site.

Inspections are where schedules slip.

Get a free quote →

Barren County permit FAQs

Who issues building permits in rural Barren County?

The City of Glasgow Building and Electrical Inspectors Office, 200 South Green Street, Suite 200, Glasgow; 270-651-3921.

How much is a permit for a new house?

$350 to $500 for the building permit depending on floor area, plus $25 plan review and $200 electrical; HVAC is $130 for the first system.

Do I need a surveyor’s plot plan?

Usually yes, unless the parcel is 10 acres or more, was created before 1978 and never changed, or is over 2 acres and the house sits at least double the setbacks with a signed waiver.

Does a farm building need a permit?

Not if it is used only for agriculture and stands on 10 acres or more; dwellings never qualify.

Can I wire my own house?

Yes, if you own it and live or will live there. Landlords and tenants cannot.

Does Barren County have zoning?

Not yet outside the cities. A county zoning ordinance and map were approved by the planning commission on October 19, 2026 and still need Fiscal Court action.

Who handles septic systems?

The Barren County Health Department, part of the Barren River District: $230 for a site evaluation (with two backhoe pits dug) and $315 for the permit.

Simplify Barren County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Kentucky. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Barren County sooner?

Let Alliance prepare, file, and track your Barren County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Barren County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.