Building permits in Salt Lake City are issued by Building Services. The city sits inside Salt Lake County but permits entirely separately from it, and separately again from the Municipal Services District that serves the unincorporated county.
This guide covers the three systems behind applying, submitting plans and paying, the published plan review queue that shows exactly how far behind review is running, when the Planning Counter should be your first stop, the city's fraud warning, and how the statewide codes apply.
This guide covers work inside Salt Lake City limits. The county, the MSD and the valley's other cities are separate authorities.
The city publishes how far behind plan review is running. Building Services posts the number of projects pending review and the submittal date currently being reviewed, separately for building code and fire code, along with monthly statistics reports. Almost no jurisdiction in the country does this — it turns programme planning from guesswork into arithmetic. Read it before you promise a date.
What requires a permit in Salt Lake City?
Salt Lake City Building Services issues building permits for work inside the city limits. The city sits inside Salt Lake County but permits entirely separately from it, and separately again from the Municipal Services District that serves the unincorporated county. The city publishes an interactive map of jurisdiction boundaries precisely because the question arises so often.
The process runs across three distinct systems, and knowing which does what saves a great deal of confusion. Applications start in the Citizen Access Portal; construction plans are submitted separately to ProjectDox for plan review; and balances due on an existing application are paid through Teller. Register in the portal, apply under the building tab, then send plans and documents through the plan review system.
Utah does something most western states do not: it adopts one construction code for the entire state. The State Construction and Fire Codes Act in Title 15A of the Utah Code sets the adopted editions, and they apply in every city, town and county rather than being chosen jurisdiction by jurisdiction. That means the question a designer has to answer here is not which edition does this city use — it is the same edition everywhere — but which local amendments, zoning standards, fire authority and service district apply on top of it.
There is a split in the current adoption that matters on every project, and getting it backwards is the most common Utah code error. Effective the first of July twenty twenty-six, Utah moved the building, plumbing, mechanical, fuel gas, energy conservation, existing building and swimming pool and spa codes to their twenty twenty-four editions. The residential code did not move — it remains the twenty twenty-one edition — and the electrical code remains the twenty twenty-three edition. So a commercial building is designed to a twenty twenty-four code while the house next door is still on twenty twenty-one, and both are correct.
Permit required
- New residential and commercial construction, additions and remodels
- Commercial change of use
- Exterior work in a historic district
- Structural alterations, relocation and demolition
- Electrical, plumbing, mechanical and gas work
- Solar photovoltaic systems and battery storage
- Work subject to fire code review alongside the building permit
- Housing standards and boarded building matters under the city's ordinances
Typically exempt
- Purely cosmetic finish work that alters no regulated system
- Like-for-like minor repairs not affecting structure or a system
- Routine maintenance that does not extend or reroute a system
- Work the city's published guidance identifies as exempt
Salt Lake City building department: who handles permitting
For some projects the Planning Counter should be your first contact, not the building counter. The city says so directly: if you are starting a project for a new structure or addition, a commercial change of use, or exterior work in a historic district, begin at Planning, where you can meet a planner and get guidance before a building application exists. Filing a building permit first on any of those three categories usually means discovering a zoning or historic issue after you have paid for drawings.
Payment mechanics have their own trap. Fees are paid online through the portal or the payment system, and paper cheques are accepted by post to the city treasury — but cheques received without an invoice cannot be processed. Send the invoice with the cheque or the payment will not be applied, which on a permit waiting for fees means the permit simply sits.
The city is also in the middle of updating the ordinances that govern how it administers building codes, covering new construction permitting, verifying housing standards and boarded building enforcement. If your project is unusual, or you are relying on a procedural position you used last year, confirm that the ordinance has not moved underneath it.
| Detail | Information |
|---|---|
| Authority | Salt Lake City Building Services |
| Apply | Citizen Access Portal, under the building tab |
| Plans | Submitted separately to the ProjectDox plan review system |
| Pay | Through the city's payment system, or by cheque with an invoice |
| Cheques | Cannot be processed if received without an invoice |
| Review queue | The city publishes pending counts and the date under review |
| Statistics | Monthly Building Services stats reports published |
| First contact | Planning Counter for new builds, change of use, historic exteriors |
| Ordinances | Building administration ordinances currently being amended |
| Governing code | Utah Title 15A statewide adopted editions |
Salt Lake City will never ask you to pay a permit fee by wire transfer. The city states it plainly: Building Services will never send an unsolicited email requesting a fee be paid by wire transfer, permit invoice notifications come from its own published address, and you should confirm any fee is legitimate before paying — through the portal, the payment system, or by contacting the office or the cashier. This is the same permit-payment fraud pattern now documented by building departments in several states. Verify by phone on a number you already have.
Salt Lake City is not Salt Lake County, and neither is the Municipal Services District. The city permits inside its own limits; the district permits unincorporated Salt Lake County and its member communities; and the valley's other cities — West Valley City, West Jordan, Sandy, South Jordan, Murray, Draper, Taylorsville, Millcreek, Holladay, Cottonwood Heights and more — each run their own departments. Use the city's published boundary map rather than the postal address.
Salt Lake City permits: record types and what each covers
The record catalog spans building, fire, planning and historic tracks, and the city reports building and fire review queues separately because they genuinely move at different speeds.
Residential permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | New dwellings, additions, and accessory structures above the local size threshold | Plan review against the jurisdiction's adopted residential code and local amendments, plus zoning and setbacks | Valuation-based |
| Addition | Added conditioned or unconditioned space attached to an existing dwelling | Structural and energy review; Utah spans several climate zones from the low desert to the high Wasatch, so envelope and equipment sizing draw attention | Valuation-based |
| Renovation / alteration | Structural changes, layout changes, or added plumbing, mechanical, or electrical | Plan review scaled to scope; a change that alters egress, structure, or a system is reviewed even where the footprint does not move | Valuation-based |
| Reroof | Roof covering replacement, recover, and structural deck repair | Deck and dry-in inspection; plan review rarely required, but a change of assembly type can trigger a structural check | Valuation or squares |
| Solar photovoltaic | Rooftop or ground-mount arrays, with or without battery storage | Single local review covering both the structural attachment and the electrical scope; there is no separate state electrical record in Utah | Flat or system-size based |
| Battery energy storage | Wall or floor-mounted storage added to a dwelling | Electrical review plus fire separation, ventilation, and location check | Flat or per-permit minimum |
| Electrical | Service changes, panel upgrades, new circuits, EV chargers, meter sets, and rewiring | Local trade review and local inspection against the National Electrical Code edition the jurisdiction has adopted | Per-permit or per-device |
| Plumbing | New piping, repipes, fixtures, gas piping, and water heater replacement | Local trade review; performed by a contractor holding the matching state licence classification and qualifier | Per-permit minimum or per-fixture |
| Mechanical / HVAC | Changeouts, new ductwork, and refrigeration | Local trade review; changeout volume is heavy given Utah heating loads and wide seasonal swings | Per-permit minimum or per-unit |
| Patio cover and shade structure | Attached and detached covers, ramadas, and carports | Structural review for wind uplift and attachment, plus zoning for setbacks and lot coverage | Valuation or flat |
| Swimming pool | In-ground and above-ground pools and spas | Barrier, bonding, and electrical review; the statewide adopted pool and spa code applies on top of local rules | Valuation or flat |
| Manufactured home set-up | Placing or re-siting a manufactured or modular home | State-level manufactured housing approval, with local zoning, floodplain, foundation, and utility connection review | Flat or per-unit |
| Demolition | Full or partial demolition of a dwelling or accessory structure | Utility disconnect confirmation, dust control where earthmoving is involved, and site restoration check | Flat |
| Historic district exterior work | Exterior work on a designated property | Start at the Planning Counter, not the building counter | Per the city schedule |
| Cheque payment | Applicants paying by post | Cheques received without an invoice cannot be processed | No surcharge |
Commercial permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New commercial construction | Ground-up commercial, industrial, and institutional buildings | Concurrent review against the jurisdiction's adopted building code and amendments, plus fire and zoning | Valuation-based |
| Tenant improvement / upfit | Interior fit-out of an existing tenant space | Building, trade, and life-safety review; accessibility attaches on change of use | Valuation-based |
| Change of occupancy | Converting a building or space to a different use group | Occupancy classification, egress, and accessibility review | Valuation or flat |
| Commercial electrical | Service, distribution, and branch circuit work | Local trade review and local inspection; Utah has no central state electrical permit for either residential or commercial work | Per-permit or valuation |
| Commercial plumbing | Process piping, fixtures, backflow, and grease waste | Local trade review; backflow and grease interceptor sign-off where applicable | Per-fixture or valuation |
| Commercial mechanical | Rooftop units, kitchen exhaust and hood systems, and refrigeration | Local trade review; hood and suppression systems draw fire review alongside mechanical | Per-unit or valuation |
| Commercial reroof | Roof covering replacement on a commercial structure | Deck, dry-in, and attachment inspection | Valuation or squares |
| Signage | Wall, ground, and illuminated signs | Zoning review for size and placement, plus electrical where illuminated | Flat or per-sign |
| Grading and drainage | Clearing, grading, and site work that alters drainage | Civil review of grading and drainage, separate from the building permit; monsoon-season flows drive the design | Acreage or valuation |
| Dust control permit | Earthmoving, trenching, and construction dust on a qualifying site | County air quality department, not the building department; required in the fine-particulate nonattainment areas | County air quality fee schedule |
| Commercial demolition | Full or partial demolition of a commercial structure | Utility disconnect, asbestos notification, dust control, and site restoration | Flat or valuation |
| Commercial change of use | Any change of occupancy classification | Also starts at the Planning Counter | Per the city schedule |
| Fire code review | Commercial and multifamily projects | Queued and reported separately from building code review | Assessed separately |
Residential
- Building and trade permits are issued and inspected by the same local authority
- There is no separate state electrical permit — electrical is a local record
- A state contractor licence in the correct classification is required, with a named qualifier where the classification demands one
- Properties on septic need on-site wastewater approval before ground is broken
Commercial — multi-discipline
- Concurrent review across building, trades, fire, and zoning
- Signed and sealed plans across every affected discipline
- The licensee's classification must match the actual scope of work
- Accessibility and life-safety review attach to any change of occupancy
Records you will actually see in Salt Lake City
| Record | What it covers |
|---|---|
| Building permit | New construction, additions, alterations and demolition in the city |
| Commercial change of use | Starting at the Planning Counter |
| Historic district exterior work | Also starting at the Planning Counter |
| Fire code review | Queued and reported separately from building review |
| Trade permit | Electrical, plumbing, mechanical and gas by the licensed contractor |
| Solar photovoltaic permit | Arrays, inverters and battery storage |
| Housing standards matter | Under the city's building administration ordinances |
| Boarded building enforcement | Also under those ordinances |
| Certificate of occupancy | Once every required inspection is clear |
Solar permits in Salt Lake City
Solar is reviewed on two tracks in Utah, but unlike some neighbouring states both tracks belong to the same government. The structural side — attachment detail, rail spacing, and whether the existing framing carries the added dead load — and the electrical side — conductors, overcurrent protection, rapid shutdown, labelling, and the service or supply-side connection — are both permitted and inspected by the local Authority Having Jurisdiction. There is no state electrical record to buy alongside the local one, and no state inspector to book.
Solar in Salt Lake City is permitted and inspected by the city, with the structural attachment and the electrical scope reviewed together. The Utah point that governs every trade here is the edition split: the building, plumbing, mechanical, fuel gas and energy codes moved to their twenty twenty-four editions in July twenty twenty-six, while the residential code stayed on twenty twenty-one and the electrical code on twenty twenty-three. A designer who reads the building code year and infers the electrical year gets rapid shutdown, labelling and conductor requirements wrong. Watch the two review queues separately on any project carrying fire review, because the city's own published figures often show building and fire running at different depths. Snow load at valley elevation is a real input on an array.
What does NOT vary here is the code edition. Because Utah adopts one and county adopts its own editions on its own timetable, the National Electrical Code edition your array is judged against in one jurisdiction may not be the one enforced a few miles away. The Office of the State Fire Marshal sets a minimum electrical standard for the state, but the edition actually enforced is the local one. Confirm it with the jurisdiction before the design is finalised rather than after a correction notice.
Interconnection runs on a third clock and is not something the building department controls. Utah properties are served by utilities including Rocky Mountain Power and a number of municipal electric systems, and UniSource, alongside municipal utilities and irrigation districts, and each sets its own application, meter and witness-test sequence. Permission to operate follows the utility's process on the utility's schedule, so plan for the tracks to finish at different times.
Roofing permits in Salt Lake City
A roof covering replacement needs a permit in most Utah jurisdictions, and the assumption that a like-for-like replacement is exempt travels badly here. The permit is usually quick, but the inspection that matters happens before the covering goes on rather than after.
Utah operates no statewide product-approval database, so there is no approval number to search for or cite on the application. The assembly has to comply with the edition of the code the jurisdiction has adopted and with the manufacturer's listed installation instructions, and that pairing is what the inspector checks — which makes the manufacturer's instructions a document worth having on site.
A roof covering replacement is permitted work and follows the ordinary sequence. On an older property near the city centre, check whether the building sits in a historic district before specifying a covering — exterior work there starts at the Planning Counter rather than the building counter. Salt Lake City roofing contends with snow load, ice damming and freeze-thaw rather than sustained desert heat.
Two Utah-specific pressures shape the work. Snow load at elevation and ultraviolet exposure age a covering faster than the same assembly would age in a milder climate, and monsoon-season wind and driven rain test the fastening and the flashing details rather than the field of the roof. Sequencing is where reroofs go wrong regardless: the deck and dry-in condition has to be visible when the inspector arrives, so covering it first means opening it back up.
Salt Lake City permit cost
Permit fees follow the city's adopted schedule, with building fees valuation-driven and plan review assessed alongside. Fees are invoiced through the portal and paid through the city's payment system, with cheques accepted by post provided the invoice accompanies them.
The cost lever specific to Salt Lake City is sequencing rather than rate. Because the city publishes its review queue, a project that files complete and early behaves very differently from one that files late into a long queue and then generates corrections. Utah jurisdictions commonly double permit fees where work has been started or completed without a permit, and several publish that rule explicitly. Treat it as the default expectation rather than an unusual penalty.
| Fee component | How it works |
|---|---|
| Building permit fee | Valuation-based under the city's adopted schedule |
| Plan review | Assessed alongside the building permit |
| Fire review | Queued and reported separately from building code review |
| Trade permits | Electrical, plumbing, mechanical and gas per discipline |
| Payment | Through the city payment system, or cheque with invoice by post |
| Historic review | Where exterior work sits in a historic district |
| Re-inspection | Charged where an inspection has to be repeated |
Want a precise number for a specific Salt Lake City project? Send us the scope and we will price the permit path before you file.
Salt Lake City trade permits
The trades are permitted and inspected by the city under Utah's statewide adopted editions. There is no central state electrical permit, so the record sits with the city while the licence behind it is a state licence.
Electrical permits
Required for service changes, panel work, new circuits, solar and EV charging. Utah's adopted electrical code did not move in the twenty twenty-six transition, so it sits a cycle behind the building code family — confirm the edition rather than inferring it.
Plumbing and gas permits
Required for new piping, repipes, fixtures, water heaters, sewer and water connections and gas piping. Salt Lake City's older housing stock means repipe and service replacement volume is high, and much of it sits in areas with historic considerations.
Mechanical permits
Required for furnaces, boilers, air conditioning, heat pumps and ductwork. The city carries a real heating load alongside summer cooling, so equipment sizing is a two-sided calculation.
Historic and planning review
Not a trade, but the review most likely to reshape a Salt Lake City project. Exterior work in a historic district, a commercial change of use and any new structure or addition all start at the Planning Counter rather than the building counter.
Salt Lake City permit application: how to apply step by step
Here is how to get a building permit in Salt Lake City, from confirming the requirement through to close-out. Each step below corresponds to a real decision point where projects commonly stall.
Salt Lake City, the Municipal Services District and the valley's other cities are separate authorities. Use the city's published jurisdiction boundary map.
New structure or addition, commercial change of use, or exterior work in a historic district all begin at the Planning Counter, where you can meet a planner before a building application exists.
The city posts pending project counts and the submittal date currently under review, separately for building code and fire code. Read it before you commit to a date.
Create an account or log in to the Citizen Access Portal and apply under the building tab, then submit construction plans to the plan review system separately.
Pay through the city's payment system, or post a cheque with the invoice. Cheques received without an invoice cannot be processed and the permit will simply wait.
The city never sends unsolicited emails requesting payment by wire transfer. Confirm a fee through the portal, the payment system or by phoning the office before paying anything.
Inspections in Salt Lake City
Inspections are requested against the issued permit through the city's systems. Because building and fire review are queued and reported separately, a project carrying both should track both — a building approval does not imply the fire side has cleared, and the city's own published figures often show the two running at different depths.
Utah gives applicants something most states do not: a route around a slow inspection queue. Under the state construction code provisions, where the jurisdiction cannot complete a requested inspection within three business days of receiving the request, inspection may be carried out by a third-party inspection firm the jurisdiction has contracted with. Some jurisdictions run the parallel route instead, entering mutual aid agreements with neighbouring cities to perform inspections when they cannot meet the same three-day standard. The procedure matters as much as the right, and skipping a step voids it. You must notify the jurisdiction before contacting a third-party inspector, and the third-party inspection is not authorised until two things have happened: the jurisdiction has confirmed it cannot complete a timely inspection itself, and you have told it you intend to use the third party. Where the route runs through a mutual aid agreement instead, use of the neighbouring jurisdiction has to be arranged with the local building inspectors first. An inspection obtained without that sequence is not a valid inspection.
In Utah the building permit is a lien document, and the mechanism is unusual enough to be worth stating plainly. Under the state's lien provisions, the local government entity that issues a building permit must, within fifteen days of issuing it, transmit the building permit information to the State Construction Registry — and that transmitted information forms the basis of the notice of commencement for the project. You do not file it; the jurisdiction does, automatically, because your permit issued. Two consequences follow. The person to whom the permit is issued is responsible for the accuracy of the information in that permit application, so an error entered at the permit counter propagates into the lien registry rather than staying a clerical detail. And because subcontractor preliminary notice deadlines run from the registry filing, the date your permit issues is effectively the date the downstream notice clock starts for everyone on the job. Check the registry entry after issuance rather than assuming it is right.
Close-out follows the ordinary sequence to the certificate of occupancy once every required inspection has passed. Where the project involved planning or historic approvals, those conditions have to be satisfied as well, so identify them at the outset rather than at final.
Salt Lake City permit search and official resources
These are the primary Salt Lake City and Utah sources behind this guide. The city is amending its building administration ordinances, so confirm the current position.
- Salt Lake City building permits
- Salt Lake City permits and licensing
- Utah Code Title 15A, State Construction and Fire Codes Act
- Utah Code Section 15A-2-103, adopted code editions
- Utah DOPL contracting
- Utah State Fire Marshal plan review
- Utah State Construction Registry
Frequently asked questions
How do I apply in Salt Lake City?
Through three connected systems. Register or log in to the Citizen Access Portal and apply under the building tab; submit construction plans separately to the ProjectDox plan review system; and pay balances through the city's payment system.
How long is plan review taking?
The city publishes the answer. Building Services posts the number of projects pending review and the submittal date currently being reviewed, separately for building code and fire code, along with monthly statistics reports. Read it before committing to a date.
When should I start at Planning instead?
For a new structure or addition, a commercial change of use, or exterior work in a historic district. The city directs those to the Planning Counter first, where you can meet a planner and get guidance before a building application exists.
Can I pay by cheque?
Yes, by post to the city treasury — but the invoice must accompany it. Cheques received without an invoice cannot be processed, which on a permit waiting for fees means the permit simply sits.
Is Salt Lake City the same as Salt Lake County?
No. The city permits inside its own limits. Unincorporated Salt Lake County and several member communities are served by the Greater Salt Lake Municipal Services District, and the valley's other cities each run their own departments.
How do I know a permit fee request is real?
The city states that Building Services will never send an unsolicited email requesting a fee be paid by wire transfer, that permit invoice notifications come from its published address, and that fees can be confirmed through the portal, the payment system, or by contacting the office or the cashier's office.
Which codes apply?
Utah's statewide adopted editions under Title 15A rather than a city-chosen edition. The building, plumbing, mechanical, fuel gas, energy, existing building and pool codes moved to twenty twenty-four editions in July twenty twenty-six; the residential code remains twenty twenty-one and the electrical code twenty twenty-three.
Are the city's ordinances changing?
Yes. Salt Lake City is updating the ordinances governing how it administers building codes, covering new construction permitting, verifying housing standards and boarded building enforcement. Confirm any procedural position you relied on previously.
What if the city cannot inspect in time?
Utah's state construction code provisions allow a third-party inspection where the jurisdiction cannot complete a requested inspection within three business days. Notify the jurisdiction first — the inspection is not authorised until it confirms it cannot inspect and you have said you intend to use the third party.
Does my permit affect lien rights?
Yes. The jurisdiction issuing a building permit must transmit the permit information to the State Construction Registry within fifteen days, and that information forms the basis of the notice of commencement. The permit holder is responsible for its accuracy.
Do I need fire sprinklers in a new house?
Not by force of the state residential code, which Utah amended to remove the model requirement for automatic sprinklers in new one- and two-family dwellings and townhouses. City fire requirements can still apply on particular projects.
Do I need a licensed contractor?
In almost all cases. Utah licenses contractors through the Division of Professional Licensing, with several classifications requiring a named qualifier. The licence is valid statewide, though city business licensing is separate.
Simplify Salt Lake City permitting with Alliance Permitting
Salt Lake City is one of the most transparent building departments in the country — it publishes its own review backlog — and the projects that struggle here are the ones that skipped Planning or filed into a queue blind. Alliance Permitting prepares, files and tracks Salt Lake City permits through issuance.
Trusted by leading builders, developers, and national contractors — 21 years of filing in the jurisdictions we write about.
Contractors and builders choose Alliance for Salt Lake City because the work is done by people who have stood at the counter:
- We read the published review queue before committing to a programme date.
- We start at Planning on new builds, change of use and historic exterior work.
- We keep the three systems straight so plans and payments land where they belong.
- We verify any unexpected fee request, because this city publishes a fraud warning for a reason.
Alliance Permitting is a permit documentation and expediting service in Utah. We are not a law firm and do not provide legal advice, and we are not the permitting authority.
Ready to break ground in Salt Lake City sooner?
Let Alliance prepare, file, and track your Salt Lake City permits while your crew stays on the job.